Under the Precedence Diagramming Method,the situation which occurs when a relationship between two tasks that can or must start at the same time is called:
A) Finish-To-Start FS)
B) Start-To-Start SS)
C) Finish-To-Finish FF)
D) Start-To-Finish SF)
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified