Multiple Choice
Which one of the following situations is more appropriate for the application of project management?
A) When none of the tasks involved in the project can be done simultaneously.
B) The need for coordination among various functional areas is high.
C) The need for coordination among various functional areas is low.
D) The project is guaranteed to be successful.
Correct Answer:

Verified
Correct Answer:
Verified