Table 35 -Using Table 3

Question 96

Multiple Choice

Table 3.5
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 6 B 3 C  A,B 2 D  A 6 E  C 2 F  D,E 2 G  C 8\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 6 \\\text { B } & \cdots & 3 \\\text { C } & \text { A,B } & 2 \\\\\text { D } & \text { A } & 6 \\\text { E } & \text { C } & 2 \\\text { F } & \text { D,E } & 2 \\\text { G } & \text { C } & 8 \\\hline\end{array}
-Using Table 3.5,what is the earliest completion time of this project?


A) less than or equal to 12 weeks
B) greater than 12 weeks but less than or equal to 14 weeks
C) greater than 14 weeks but less than or equal to 16 weeks
D) greater than 16 weeks

Correct Answer: