Multiple Choice
A PERT project has 45 activities,19 of which are on the critical path.The estimated time for the critical path is 120 days.The sum of all activity variances is 64,while the sum of variances along the critical path is 36.What is the probability that the project can be completed between days 108 and 120?
A) -2.00
B) 0.0227
C) 0.1058
D) 0.4773
E) 0.9773
Correct Answer:

Verified
Correct Answer:
Verified
Q15: The _ is a project management technique
Q37: WBS stands for which of the following
Q72: What is the objective of critical path
Q72: A simple CPM network has three activities,D,E,and
Q74: Ethical issues that may arise in projects
Q75: Analysis of a PERT problem shows the
Q78: Three critical path activities are candidates for
Q79: Activity D on a CPM network has
Q81: A network consists of the activities in
Q82: Two critical path activities are candidates for