Multiple Choice
Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.
A) B;$2,000
B) B;$8,000
C) C;$1,000
D) C;$2,000
E) C;$6,000
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q15: The _ is a project management technique
Q27: The PERT pessimistic time estimate is an
Q47: One phase of a large project is
Q75: A project manager is interested in crashing
Q77: A PERT project has 45 activities,19 of
Q78: Three critical path activities are candidates for
Q79: Activity D on a CPM network has
Q81: A network consists of the activities in
Q85: Which of the following is NOT one
Q86: The ES of an activity that has