Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for each of the three activities?
b.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
c.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
Correct Answer:

Verified
(a)crash cost X = $1,000 per d...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q15: The _ is a project management technique
Q37: WBS stands for which of the following
Q72: What is the objective of critical path
Q74: Ethical issues that may arise in projects
Q75: Analysis of a PERT problem shows the
Q75: A project manager is interested in crashing
Q77: A PERT project has 45 activities,19 of
Q79: Activity D on a CPM network has
Q81: A network consists of the activities in
Q82: Two critical path activities are candidates for