Essay
A network consists of the activities in the following list.Times are given in weeks.
a.Draw the network diagram.
b.Calculate the ES,EF,LS,LF,and Slack for each activity.
c.What is project completion time?
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q15: The _ is a project management technique
Q27: The PERT pessimistic time estimate is an
Q47: One phase of a large project is
Q72: What is the objective of critical path
Q75: A project manager is interested in crashing
Q77: A PERT project has 45 activities,19 of
Q78: Three critical path activities are candidates for
Q79: Activity D on a CPM network has
Q82: Two critical path activities are candidates for
Q85: Which of the following is NOT one