Solved

Given the Project Within the Table Below,calculate the Following

Question 117

Essay

Given the project within the table below,calculate the following:
a.The critical path
b.The minimum project duration
c.The amount of slack for each activity
Given the project within the table below,calculate the following: a.The critical path b.The minimum project duration c.The amount of slack for each activity

Correct Answer:

verifed

Verified

blured image (A)The critical path is CDEFG
(B)Minimu...