Multiple Choice
Table J.2
Suppose that the following six jobs must be scheduled through a car repair facility:
-Use the information in Table J.2.Which one of the following jobs will be the last one completed if sequencing is done using the FCFS rule?
A) A
B) B
C) C
D) D
Correct Answer:

Verified
Correct Answer:
Verified