Multiple Choice
Table J.5
The following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.
-Use the information in Table J.5. The operations sequence of jobs, using the critical ratio (CR) rule, is
A) 3-1-2
B) 3-2-1
C) 1-2-3
D) 2-3-1
Correct Answer:

Verified
Correct Answer:
Verified