Multiple Choice
Table 5.3
King Supply makes four different types of plumbing fixtures: W, X, Y and Z. The contribution margins for these products are: $70 for Product W, $60 for Product X, $90 for Product Y and $100 for Product Z. Fixed overhead is estimated at $5,500 per week. The manufacture of each fixture requires four machines, Machines #1, 2, 3 and 4. Each of the machines is available for 40 hours a week and there is no setup time required when shifting from the production of one product to any other. The processing requirements to make one unit of each product are shown in the table. Weekly product demand for the next planning period has been forecasted as follows: 70 Ws, 60 Xs, 50 Ys and 30 Zs.
In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 5.3. Using the traditional method, in what sequence should the fixtures be scheduled for production?
A) Z, Y, X, W
B) X, W, Z, Y
C) Z, Y, W, X
D) W, X, Y, Z
Correct Answer:

Verified
Correct Answer:
Verified
Q126: An assembly line has to perform 10
Q127: Table 5.1<br>A company makes four products that
Q128: Table 5.7<br>The Terminal Company is attempting to
Q129: Table 5.5<br>Balance the following line for an
Q130: Balance the assembly line using the following
Q131: What is the definition of "theoretical maximum
Q132: Table 5.4<br>The Superior Management Company assembles muffalettas
Q133: What are five of the seven key
Q135: Table 5.1<br>A company makes four products that
Q136: A line that produces several items belonging