Exam 3: Managing Systems Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A continuous risk-tracking process can _____.

(Multiple Choice)
4.9/5
(38)

_____,a human resource issue,is a possible cause of cost overruns in an organization.

(Multiple Choice)
4.9/5
(42)

_____ give team members of a project an opportunity to share information,discuss common problems,and explain new techniques.

(Multiple Choice)
4.9/5
(28)

Explain the difference between qualitative and quantitative risk analysis.

(Essay)
4.8/5
(39)

GanttProject is a free open-source Java-based project management tool that is available on multiple platforms.

(True/False)
4.8/5
(45)

Project planning,an activity of a project manager,_____.

(Multiple Choice)
4.8/5
(38)

Often,two or more concurrent tasks depend on a single prior task,which is called a _____.

(Multiple Choice)
4.7/5
(38)

When tasks must be completed one after another,they are called concurrent tasks.

(True/False)
4.9/5
(39)

A _____ displays the same information as the Gantt chart,including task dependencies,but uses task boxes to include much more detail.

(Multiple Choice)
4.7/5
(37)

The first step in creating a work breakdown structure (WBS)is to _____.

(Multiple Choice)
4.9/5
(40)

A(n)_____ is a series of tasks that,if delayed,would affect the completion date of the overall project.

(Multiple Choice)
4.9/5
(36)

Weight is an importance value that is added to each duration estimate.

(True/False)
4.8/5
(44)

_____ give the project managers an opportunity to seek input and conduct brainstorming sessions.

(Multiple Choice)
4.8/5
(32)

System developers can initiate a formal project as early as the preliminary investigation stage,or later on,as analysis,design,and implementation activities occur.

(True/False)
4.9/5
(36)

Explain the three legs of a project triangle.What makes it challenging?

(Essay)
4.7/5
(25)

Two or more _____ depend on a predecessor task.

(Multiple Choice)
4.9/5
(32)

Using a work breakdown structure (WBS)allows one to manage a project as one large task.

(True/False)
4.9/5
(46)

Project scheduling,an activity of a project manager,_____.

(Multiple Choice)
4.8/5
(39)

_____,a free cloud-based project management tool,runs in a browser window,so there is no software to install to use it.

(Multiple Choice)
4.9/5
(47)

The first step in the creation of a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM)chart is to _____.

(Multiple Choice)
5.0/5
(43)