Exam 3: Managing Systems Projects
Exam 1: Introduction to Systems Analysis and Design80 Questions
Exam 2: Analyzing the Business Case80 Questions
Exam 3: Managing Systems Projects80 Questions
Exam 4: Requirements Engineering79 Questions
Exam 5: Data and Process Modeling80 Questions
Exam 6: Object Modeling74 Questions
Exam 7: Development Strategies80 Questions
Exam 8: User Interface Design79 Questions
Exam 9: Data Design80 Questions
Exam 10: System Architecture80 Questions
Exam 11: Managing Systems Implementation80 Questions
Exam 12: Managing Systems Support and Security80 Questions
Exam 13: Communication-Tools45 Questions
Exam 14: Case-Tools45 Questions
Exam 15: Financial-Analysis-Tools42 Questions
Exam 16: Internet-Resource-Tools44 Questions
Select questions type
A(n)_____ is a condition,restriction,or requirement that the system must satisfy.
Free
(Multiple Choice)
4.9/5
(30)
Correct Answer:
A
Mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days,but most likely will require 20 days.What is the 20 day estimate called?
Free
(Multiple Choice)
4.7/5
(36)
Correct Answer:
B
A _____ involves breaking a project down into a series of smaller tasks.
Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
A
Critical time is the amount of time that the task could be late without pushing back the completion date of the entire project.
(True/False)
4.8/5
(33)
A _____ might involve maximums for one or more resources,such as time,dollars,or people.
(Multiple Choice)
4.7/5
(37)
Quantitative risk analysis evaluates each risk by estimating the probability that it will occur and the degree of impact.
(True/False)
4.8/5
(37)
When maintaining schedules,if enough _____ and frequent checkpoints exist,problems will be detected rapidly.
(Multiple Choice)
4.7/5
(35)
_____ is a full-featured program that holds the dominant share of the project management software market.
(Multiple Choice)
4.7/5
(41)
If any task along a critical path falls behind schedule,the entire project will be delayed.
(True/False)
4.8/5
(42)
The three legs of a project triangle are _____,scope,and time.
(Multiple Choice)
4.8/5
(42)
Progress reports may be given verbally to immediate supervisors,management,and users.
(True/False)
4.8/5
(35)
A _____ represents the work that one person can complete in one day.
(Multiple Choice)
4.9/5
(30)
A Gantt chart can simplify a complex project by combining several activities into a task _____ that contains subsidiary tasks.
(Multiple Choice)
4.7/5
(31)
A(n)_____ is an event that could affect a project negatively.
(Multiple Choice)
4.8/5
(35)
A _____ includes a review of a project's scope,stakeholders,budget,schedule,and any other internal or external factors that might affect the project.
(Multiple Choice)
4.8/5
(35)
The purpose of quantitative risk analysis is to understand the actual impact in terms of dollars,time,project scope,or quality.
(True/False)
4.9/5
(34)
In a Program Evaluation Review Technique (PERT)/Critical Path Method (CPM)chart,each rectangular box,called a task box,has five sections that contain important information about a task.
(True/False)
4.8/5
(34)