Exam 13: Resource Planning
Exam 1: Creating Customer Value128 Questions
Exam 2: Supply Chain Management170 Questions
Exam 3: Supply Chain Sustainability and Humanitarian Logistics132 Questions
Exam 4: Process Configuration132 Questions
Exam 5: Capacity143 Questions
Exam 6: Waiting Lines165 Questions
Exam 7: Inventory Management218 Questions
Exam 8: Quality and Process Improvement153 Questions
Exam 9: Lean Systems112 Questions
Exam 10: Location and Layout216 Questions
Exam 11: Managing Demand and Forecasting189 Questions
Exam 12: Operations Planning and Scheduling134 Questions
Exam 13: Resource Planning174 Questions
Select questions type
Dependent demand occurs because the quantity required is a function of the demand for other items held in inventory.
(True/False)
4.8/5
(33)
Table 13.3
Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s).
Master Production Schedule: the following table shows the MPS start quantities.
Week
Week 1 2 3 4 5 6 A 50 80 100 B 60 100
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
Data Category Lot-sizing rule 4 4 FOQ =250 POQ (=2) Lead time (wks) 3 1 3 1 Beginning (on-hand) inventory 50 80 90 30 Scheduled receipts 80(1) None 250(3) 205(1)
-Use the information in Table 13.3. Which one of the following statements on item C is TRUE?
(Multiple Choice)
4.9/5
(40)
In a dependent demand environment, explained why MRP does a better job of estimating the need to replenish inventory items than does a fixed order quantity system.
(Essay)
4.8/5
(41)
_________ are orders that have been placed, but not yet completed.
(Short Answer)
4.8/5
(40)
_________ systems are large, integrated information systems that support many enterprise processes and data storage needs.
(Short Answer)
4.9/5
(35)
_________ is an algorithm designed to schedule a group of orders appropriately across an entire shop.
(Short Answer)
4.7/5
(34)
Table 13.8
Sunshine Manufacture produces three products, X, Y, and Z. The production of these end items is controlled by an MRP system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled with two components of C and one component of A, each component of C is manufactured from one unit of B. End item Z is assembled from one unit of D and one unit of C, D is manufactured from one unit of A, and C is manufactured from one unit of B.
-Use the information in Table 13.8. If level- by- level processing is used, what is a correct order for processing components A, B, C, and D?
(Multiple Choice)
4.8/5
(25)
_________ demand occurs because the quantity required is a function of the demand for the other items held in inventory.
(Short Answer)
4.8/5
(43)
Which best defines the gross requirements for a component item?
(Multiple Choice)
4.8/5
(40)
Table 13.7.
-Use the information from Table 13.7. If a POQ lot- sizing rule is used, where P = 3, how many planned order releases are there for item XYZ?

(Multiple Choice)
4.8/5
(35)
The _________ is a record of all components of an item, the parent- component relationships, and usage quantities derived from engineering and process design.
(Short Answer)
4.9/5
(40)
The lot- sizing rule that generates the highest level of average inventory because it creates inventory remnants is
(Multiple Choice)
4.9/5
(33)
Material requirements planning (MRP) is a computerized information system developed specifically to aid in managing dependent demand inventory and scheduling replenishment orders.
(True/False)
4.9/5
(37)
Management wishes to use a FOQ lot- sizing rule for an item based on the economic order quantity. If the annual demand is 1200 units, the holding cost is $10/unit/year, and the setup cost is $50/lot, which one of the following fixed order quantities is most appropriate?
(Multiple Choice)
4.9/5
(34)
Lumpy dependent demand can result from continuous independent demand.
(True/False)
5.0/5
(31)
An action bucket is the first week's entry of the planned order release row.
(True/False)
4.9/5
(38)
Showing 81 - 100 of 174
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)