Exam 13: Resource Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The _________ rule is a special case of the periodic order quantity (POQ) rule where the lot size ordered covers the gross requirements of a single time period (e.g. one week).

(Short Answer)
4.9/5
(32)

Management wishes to use a POQ lot- sizing rule for an item that experiences an average demand of 30 units per week. If the desired average lot size is 120 units, what should P be?

(Multiple Choice)
4.9/5
(38)

Faster response to market changes and reduced inventory levels are both benefits of MRP.

(True/False)
4.9/5
(37)

Lot- for- lot (L4L) is a rule that maintains the same order quantity each time an order is issued.

(True/False)
4.9/5
(42)

_________ is an inventory control and scheduling technique that applies MRP principles to distribution inventories.

(Short Answer)
4.9/5
(44)

Explain the major difference for resource planning in service firms compared to manufacturers.

(Essay)
4.8/5
(36)

Which one of the following is a feature of MRP II, but not available in basic MRP systems?

(Multiple Choice)
4.8/5
(39)

Table 13.3 Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s). Master Production Schedule: the following table shows the MPS start quantities. Week Week 1 2 3 4 5 6 A 50 80 100 B 60 100 Bill of Material -End item A uses 1 each of component C and 1 each of subassembly D. -Subassembly D uses 2 each of component E and 2 each of component F. -End item B uses 1 each of component C and 2 each of component F. Selected Inventory Data Item Data Category Lot-sizing rule 4 4 FOQ =250 POQ (=2) Lead time (wks) 3 1 3 1 Beginning (on-hand) inventory 50 80 90 30 Scheduled receipts 80(1) None 250(3) 205(1) -Use the information in Table 13.3. Which one of the following statements about item C is TRUE?

(Multiple Choice)
4.8/5
(31)

_________ ties the basic MRP system to the company's financial system.

(Short Answer)
4.8/5
(40)

Which one of the following systems is an input to the MRP system?

(Multiple Choice)
4.8/5
(37)

The _________ is a part of the material requirements plans that details how many end items will be produced within specified periods of time.

(Short Answer)
4.8/5
(36)

In an MRP system, a(n) _________ item has at least one parent and at least one component.

(Short Answer)
4.9/5
(34)

_________ is a computerized information system developed specifically to aid in managing dependent demand inventory and scheduling replenishment orders.

(Short Answer)
4.9/5
(36)

A bill of materials lists all components, ingredients, as and materials needed to produce one unit of an end item.

(True/False)
4.8/5
(38)

Explain why MRP does a better job of estimating the need to replenish inventory items than does the fixed order quantity system in a dependent demand environment.

(Essay)
4.7/5
(33)

Complete the following MRP schedule: Complete the following MRP schedule:

(Essay)
4.8/5
(39)

The underlying logic for level- by- level processing in an MRP system is

(Multiple Choice)
4.8/5
(44)

Part commonality refers to a degree to which a component has more than one immediate parent.

(True/False)
4.7/5
(37)

Safety stock is more complex for independent demand items than for dependent demand items.

(True/False)
4.8/5
(41)

MRP explosion means estimating the total number of

(Multiple Choice)
4.8/5
(39)
Showing 141 - 160 of 174
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)