Exam 17: Standard Costing and Variance Analysis 1

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

During September, 40,000 units of product were produced. The standard quantity of material allowed per unit was four pounds at a standard cost of £6.00 per pound. If there was a favourable materials usage variance of £30,000 for April, the actual quantity of materials used must be

(Multiple Choice)
4.8/5
(34)

Which of the following is information that would be included in the standard cost card (sheet)?

(Multiple Choice)
5.0/5
(32)

For better control of direct material prices, when should direct material price variance be recognized?

(Multiple Choice)
4.8/5
(28)

Using more highly skilled direct labourers might affect which of the following variances?

(Multiple Choice)
4.8/5
(30)

Franklin Company expected sales were 2,000 units at £100 per unit. During 2011, it had actual sales of 1,800 units at £110 per unit. Budgeted variable costs were £60 per unit. What is Franklin's sales price variance?

(Multiple Choice)
4.7/5
(34)

Figure 17-7 Orient Company has developed the following standards for one of its products: Direct materials 10 pounds \times£8 per pound Direct labour 6 hours \times£20 per hour Variable overhead 6 hours \times£6 per hour The following activities occurred during the month of November: Materials purchased 8,000 pounds costing £70,000 Materials used 6,500 pounds Units produced 600 units Direct labour 4,200 hours costing £75,600 Actual variable overhead £26,400 The company records materials price variances at the time of purchase. -Refer to Figure 17-7. Orient's labour efficiency variance would be

(Multiple Choice)
4.7/5
(41)

During October, 16,000 direct labour hours were worked at a standard cost of £6 per hour. If the labour rate variance for October was £4,000 unfavourable, the actual cost per labour hour must be

(Multiple Choice)
4.8/5
(37)

During December, 6,000 pounds of raw materials were purchased at a cost of £16 per pound. If there was an unfavourable materials price variance of £6,000 for December, the standard cost per pound must be

(Multiple Choice)
4.9/5
(29)

Figure 17-6 Budgeted fixed overhead for the year £300,000 Budgeted direct labour hours for the year 30,000 Actual fixed overhead for August £24,000 Actual variable overhead for August £10,000 Direct labour hours worked in August 2,600 Standard variable overhead cost per direct labour hour £4 Standard direct labour hours allowed for August production 2,750 -Refer to Figure 17-6. The fixed overhead spending variance would be

(Multiple Choice)
4.7/5
(34)

Figure 17-1 Max Company has developed the following standards for one of its products: Direct materials 15 pounds \times£16 per pound Direct labour 4 hours \times£24 per hour Variable overhead 4 hours \times£14 per hour The following activities occurred during the month of October: Materials purchased 10,000 pounds costing £170,000 Materials used 7,200 pounds Units produced 500 units Direct labour 2,300 hours at £23.60 per hour Actual variable overhead £30,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-1. Max's labour efficiency variance would be

(Multiple Choice)
4.9/5
(40)

Figure 17-6 Budgeted fixed overhead for the year £300,000 Budgeted direct labour hours for the year 30,000 Actual fixed overhead for August £24,000 Actual variable overhead for August £10,000 Direct labour hours worked in August 2,600 Standard variable overhead cost per direct labour hour £4 Standard direct labour hours allowed for August production 2,750 -Refer to Figure 17-6. The fixed overhead volume variance would be

(Multiple Choice)
4.8/5
(39)

Figure 17-1 Max Company has developed the following standards for one of its products: Direct materials 15 pounds \times£16 per pound Direct labour 4 hours \times£24 per hour Variable overhead 4 hours \times£14 per hour The following activities occurred during the month of October: Materials purchased 10,000 pounds costing £170,000 Materials used 7,200 pounds Units produced 500 units Direct labour 2,300 hours at £23.60 per hour Actual variable overhead £30,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-1. Max's variable standard cost per unit would be

(Multiple Choice)
4.8/5
(34)

Figure 17-1 Max Company has developed the following standards for one of its products: Direct materials 15 pounds \times£16 per pound Direct labour 4 hours \times£24 per hour Variable overhead 4 hours \times£14 per hour The following activities occurred during the month of October: Materials purchased 10,000 pounds costing £170,000 Materials used 7,200 pounds Units produced 500 units Direct labour 2,300 hours at £23.60 per hour Actual variable overhead £30,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-1. Max's materials price variance would be

(Multiple Choice)
4.9/5
(43)

Standard cost systems can enhance operational control through the use of

(Multiple Choice)
4.8/5
(36)

Figure 17-6 Budgeted fixed overhead for the year £300,000 Budgeted direct labour hours for the year 30,000 Actual fixed overhead for August £24,000 Actual variable overhead for August £10,000 Direct labour hours worked in August 2,600 Standard variable overhead cost per direct labour hour £4 Standard direct labour hours allowed for August production 2,750 -Refer to Figure 17-6. The standard rate for total overhead is

(Multiple Choice)
4.8/5
(37)

Figure 17-7 Orient Company has developed the following standards for one of its products: Direct materials 10 pounds \times£8 per pound Direct labour 6 hours \times£20 per hour Variable overhead 6 hours \times£6 per hour The following activities occurred during the month of November: Materials purchased 8,000 pounds costing £70,000 Materials used 6,500 pounds Units produced 600 units Direct labour 4,200 hours costing £75,600 Actual variable overhead £26,400 The company records materials price variances at the time of purchase. -Refer to Figure 17-7. Orient's materials usage variance would be

(Multiple Choice)
4.7/5
(34)

Figure 17-4 Shannon Ltd.'s standard cost card contained the following information: Direct labour: 1.25 hours * £8.00 per hour = £10.00 Shannon planned to make 12,000 units. Shannon actually made 10,000 units using 13,000 hours. -Refer to Figure 17-4. Shannon's standard hours allowed for production was

(Multiple Choice)
4.8/5
(29)

Figure 17-2 Rax Company has developed the following standards for one of its products: Direct materials 12 pounds * £14 per pound Direct labour 3 hours * £18 per hour Variable overhead 3 hours * £8 per hour The following activities occurred during the month of October: Materials purchased 10,000 pounds at £13.60 per pound Materials used 9,000 pounds Units produced 800 units Direct labour 2,500 hours at £19.00 per hour Actual variable overhead £22,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-2. Rax's materials price variance would be

(Multiple Choice)
4.8/5
(33)

Figure 17-4 Shannon Ltd.'s standard cost card contained the following information: Direct labour: 1.25 hours * £8.00 per hour = £10.00 Shannon planned to make 12,000 units. Shannon actually made 10,000 units using 13,000 hours. -Refer to Figure 17-4. If Shannon's actual labour cost was £136,500, Shannon's labour rate variance was

(Multiple Choice)
4.9/5
(37)

During May, 6,000 pounds of raw materials were purchased at a cost of £2.60 per pound. If there was a favourable materials price variance of £900 for December, the standard cost per pound must be

(Multiple Choice)
4.9/5
(38)
Showing 61 - 80 of 81
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)