Exam 17: Standard Costing and Variance Analysis 1

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Who is responsible for unfavourable labour efficiency variances caused by poor quality materials?

(Multiple Choice)
4.7/5
(34)

The following standard costs were developed for one of Commodore Company's products: STANDARD COST CARD PER UNIT Direct materials: 4 pounds \times£5 per pound £20.00 Direct labour: 1.5 hours \times£20 per hour 30.00 Variable overhead: £10 per hour ? Fixed overhead Total standard cost per unit The following information is available regarding the company's operations for the period: Units produced 15,000 Materials purchased 90,000 pounds at £3.60 per pound Materials used 80,000 pounds Direct labour 9,000 hours at £16.50 per hour Overhead incurred: Variable £220,000 Fixed £640,000 Budgeted fixed overhead for the period is £600,000, and expected capacity for the period is 20,000 direct labour hours. a.Calculate the standard fixed overhead rate. b.Complete the standard cost card for the product.

(Essay)
4.9/5
(35)

Figure 17-7 Orient Company has developed the following standards for one of its products: Direct materials 10 pounds \times£8 per pound Direct labour 6 hours \times£20 per hour Variable overhead 6 hours \times£6 per hour The following activities occurred during the month of November: Materials purchased 8,000 pounds costing £70,000 Materials used 6,500 pounds Units produced 600 units Direct labour 4,200 hours costing £75,600 Actual variable overhead £26,400 The company records materials price variances at the time of purchase. -Refer to Figure 17-7. Orient's variable overhead efficiency variance would be

(Multiple Choice)
4.9/5
(37)

Figure 17-1 Max Company has developed the following standards for one of its products: Direct materials 15 pounds \times£16 per pound Direct labour 4 hours \times£24 per hour Variable overhead 4 hours \times£14 per hour The following activities occurred during the month of October: Materials purchased 10,000 pounds costing £170,000 Materials used 7,200 pounds Units produced 500 units Direct labour 2,300 hours at £23.60 per hour Actual variable overhead £30,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-1. Max's labour rate variance would be

(Multiple Choice)
4.9/5
(35)

Figure 17-1 Max Company has developed the following standards for one of its products: Direct materials 15 pounds \times£16 per pound Direct labour 4 hours \times£24 per hour Variable overhead 4 hours \times£14 per hour The following activities occurred during the month of October: Materials purchased 10,000 pounds costing £170,000 Materials used 7,200 pounds Units produced 500 units Direct labour 2,300 hours at £23.60 per hour Actual variable overhead £30,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-1. Max's materials usage variance would be

(Multiple Choice)
4.8/5
(42)

Fortensky Construction planned to produce 275,000 units using 34,375 machine hours. Actual output was 290,000 units using 37,425 machine hours. Fortensky's volume variance

(Multiple Choice)
4.7/5
(36)

The sales price variance is created by a difference between

(Multiple Choice)
4.9/5
(34)

The labour rate variance is calculated as

(Multiple Choice)
4.8/5
(44)

Figure 17-5 Ebola Company has developed the following standards for one of its products: Direct materials 20 pounds \times£4 per pound Direct labour 5 hours \times£18 per hour Variable overhead 5 hours \times£4 per hour The following activities occurred during the month of October: Materials purchased 230,000 pounds at £4.20 per pound Materials used 220,000 pounds Units produced 10,000 units Direct labour 51,000 hours at £17.70 per hour Actual variable overhead £240,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-5. Ebola's variable overhead efficiency variance would be

(Multiple Choice)
4.9/5
(34)

Figure 17-3 Tuvok Ltd. has developed the following standards for one of its products: Standard cost of materials £0.50 per pound Materials purchased and used 20,000 pounds Total paid to suppliers £11,000 Standard quantity allowed 18,000 pounds -Refer to Figure 17-3. Tuvok's material price variance is

(Multiple Choice)
4.9/5
(45)

For planning and control purposes, fixed overhead is NOT included in the standard cost per unit because:

(Multiple Choice)
4.8/5
(27)

Figure 17-5 Ebola Company has developed the following standards for one of its products: Direct materials 20 pounds \times£4 per pound Direct labour 5 hours \times£18 per hour Variable overhead 5 hours \times£4 per hour The following activities occurred during the month of October: Materials purchased 230,000 pounds at £4.20 per pound Materials used 220,000 pounds Units produced 10,000 units Direct labour 51,000 hours at £17.70 per hour Actual variable overhead £240,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-5. Ebola's materials price variance would be

(Multiple Choice)
4.9/5
(40)

If a company was concerned with controlling expenditures on overhead items, which variance would be useful?

(Multiple Choice)
4.9/5
(42)

During October, 14,000 direct labour hours were worked at a standard cost of £40 per hour. If the labour rate variance for October was £70,000 favourable, the actual cost per labour hour must be

(Multiple Choice)
4.8/5
(28)

If actual fixed overhead was £164,000 and there was a £4,800 favourable spending variance and a £1,000 unfavourable volume variance, budgeted fixed overhead must have been

(Multiple Choice)
4.8/5
(37)

Figure 17-2 Rax Company has developed the following standards for one of its products: Direct materials 12 pounds * £14 per pound Direct labour 3 hours * £18 per hour Variable overhead 3 hours * £8 per hour The following activities occurred during the month of October: Materials purchased 10,000 pounds at £13.60 per pound Materials used 9,000 pounds Units produced 800 units Direct labour 2,500 hours at £19.00 per hour Actual variable overhead £22,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-2. Rax's labour rate variance would be

(Multiple Choice)
5.0/5
(35)

During April, 80,000 units of product were produced. The standard quantity of material allowed per unit was two pounds at a standard cost of £5 per pound. If there was a favourable materials usage variance of £40,000 for April, the actual quantity of materials used must have been

(Multiple Choice)
4.8/5
(36)

The following standard costs were developed for one of Commodore Company's products: STANDARD COST CARD PER UNIT Direct materials: 3 pounds \times£2 per pound £6.00 Direct labour: 2 hours \times£12 per hour 24.00 Variable overhead: £4 per hour ? Fixed overhead Total standard cost per unit ? The following information is available regarding the company's operations for the period: Units produced 12,000 Materials purchased 50,000 pounds at £2 per pound Materials used 40,000 pounds Direct labour 25,000 hours at £13 per hour Overhead incurred: Variable £90,000 Fixed £300,000 Budgeted fixed overhead for the period is £280,000, and expected capacity for the period is 28,000 direct labour hours. a.Calculate the standard fixed overhead rate. b.Complete the standard cost card for the product.

(Essay)
4.9/5
(40)

Figure 17-6 Budgeted fixed overhead for the year £300,000 Budgeted direct labour hours for the year 30,000 Actual fixed overhead for August £24,000 Actual variable overhead for August £10,000 Direct labour hours worked in August 2,600 Standard variable overhead cost per direct labour hour £4 Standard direct labour hours allowed for August production 2,750 -Refer to Figure 17-6. The variable overhead spending variance would be

(Multiple Choice)
4.9/5
(30)

Efficiency variances focus on the difference between

(Multiple Choice)
4.9/5
(41)
Showing 41 - 60 of 81
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)