Exam 3: Managing Systems Projects
Exam 1: Introduction to Systems Analysis and Design80 Questions
Exam 2: Analyzing the Business Case81 Questions
Exam 3: Managing Systems Projects78 Questions
Exam 4: Requirements Modeling98 Questions
Exam 5: Data and Process Modeling84 Questions
Exam 6: Object Modeling78 Questions
Exam 7: Development Strategies82 Questions
Exam 8: User Interface Design82 Questions
Exam 9: Data Design86 Questions
Exam 10: System Architecture78 Questions
Exam 11: Managing Systems Implementation81 Questions
Exam 12: Managing Systems Support and Security81 Questions
Exam 13: Appendix-The Systems Analyst’s Toolkit45 Questions
Exam 14: CASE Tools45 Questions
Exam 15: Financial Analysis Tools45 Questions
Exam 16: Internet Resource Tools44 Questions
Select questions type
When tasks must be completed one after another, they are called concurrent tasks.
(True/False)
4.9/5
(37)
A(n) _____ is a series of tasks that, if delayed, would affect the completion date of the overall project.
(Multiple Choice)
4.7/5
(36)
A _____ displays the same information as the Gantt chart, including task dependencies, but uses task boxes to include much more detail.
(Multiple Choice)
4.8/5
(33)
A _____ represents the work that one person can complete in one day.
(Multiple Choice)
5.0/5
(31)
Matching
Identify the letters of the choices that best match the phrases or definitions.
-A recognizable reference point that can be used to monitor progress and manage a project
(Multiple Choice)
4.7/5
(42)
_____ give team members of a project an opportunity to share information, discuss common problems, and explain new techniques.
(Multiple Choice)
4.9/5
(42)
A _____ involves breaking a project down into a series of smaller tasks.
(Multiple Choice)
4.7/5
(39)
Matching
Identify the letters of the choices that best match the phrases or definitions.
-Tasks that must be completed before another task can start.
(Multiple Choice)
4.8/5
(38)
Mauricio, a project manager at a reputed firm, has been assigned to handle a new project that the firm has received. This project involves a lot of scheduling that has to be handled by Mauricio.
-Mauricio has decided to use a project management tool for this project. He wants the tool to be free and cloud-based so that there is no need for software to be installed. Help Mauricio in identifying the project management tool that best fits the purpose.
(Multiple Choice)
4.9/5
(38)
-A task that represents several activities is known as a _____.

(Multiple Choice)
4.9/5
(40)
A _____ is a review of a project team member's work by other members of a team.
(Multiple Choice)
5.0/5
(36)
A(n) _____ is a condition, restriction, or requirement that the system must satisfy.
(Multiple Choice)
4.8/5
(34)
Generally, systems analysts review the work of other systems analysts, and programmers review the work of other programmers, as a form of peer review, in structured walk-throughs.
(True/False)
4.9/5
(31)
A _____ includes a review of a project's scope, stakeholders, budget, schedule, and any other internal or external factors that might affect the project.
(Multiple Choice)
4.8/5
(33)
Microsoft claims that the Microsoft Project software can _____.
(Multiple Choice)
4.8/5
(42)
-A(n) _____ is any work that has a beginning and an end and requires the use of company resources such as people, time, or money.

(Multiple Choice)
4.8/5
(38)
A(n) _____ is a recognizable reference point that can be used to monitor progress.
(Multiple Choice)
5.0/5
(38)