Exam 6: Resource Utilisation
Exam 1: Project Management Concepts78 Questions
Exam 2: Identifying and Selecting Projects69 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility and Activity Sequence115 Questions
Exam 5: Developing the Schedule83 Questions
Exam 6: Resource Utilisation22 Questions
Exam 7: Determining Costs, Budget and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project41 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organisational Structures65 Questions
Select questions type
-Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question: If the tasks were placed in a serial relationship with Task 1 first and the others in numerical order, on what day would Task 3 be done?

(Multiple Choice)
4.8/5
(33)
The statement, 'Network diagrams illustrate the technical constraints among activities', means the activities are constrained because
(Multiple Choice)
4.8/5
(31)
Showing 21 - 22 of 22