Exam 6: Resource Utilisation

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Resource-limited scheduling is a method for

Free
(Multiple Choice)
4.9/5
(39)
Correct Answer:
Verified

D

Which of following would allow for level resources on the project?

Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
Verified

C

  -Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question: What is the least number of resources that can be assigned to the project if all five tasks occur in parallel? -Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question: What is the least number of resources that can be assigned to the project if all five tasks occur in parallel?

Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
Verified

C

Activities can be delayed only to the point where all their positive slack is used up, as any further delays would cause the project to

(Multiple Choice)
4.8/5
(40)

assist with the complexity of generating a resource-levelled schedule and resource requirements graphs and tables.

(Multiple Choice)
4.9/5
(40)

The start of non-critical activities are delayed beyond their earliest start times (but not beyond their latest start times) in order to

(Multiple Choice)
4.7/5
(34)

Resource-limited scheduling will not extend the project completion time if necessary in order to keep within the resource limits.

(True/False)
4.7/5
(43)

A resource requirements plan illustrates

(Multiple Choice)
4.8/5
(38)

When several activities need the same limited resource at the same time, the activities with

(Multiple Choice)
4.8/5
(28)

Why are activities drawn in a serial relationship in a network diagram?

(Multiple Choice)
4.9/5
(29)

Resource utilisation charts based on each activity's latest start time are said to be based on

(Multiple Choice)
4.7/5
(38)

Select which of the following does not describe how the sequence of activities can be drawn to reflect the availability of a limited quantity of resources.

(Multiple Choice)
4.8/5
(50)

This example has level resources of three resources for eight days.If the project is limited to two resources, how should the project be organised to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number. This example has level resources of three resources for eight days.If the project is limited to two resources, how should the project be organised to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.

(Multiple Choice)
4.8/5
(33)

In resource-limited scheduling, the lower priority activities get delayed.How does the delaying of activities affect the project?

(Multiple Choice)
4.8/5
(36)

  -Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question: What is the least amount of time that the project can be completed and how many resources are required to complete the work? -Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question: What is the least amount of time that the project can be completed and how many resources are required to complete the work?

(Multiple Choice)
4.8/5
(40)

Resource utilisation charts based on each activity's earliest start time are said to be based on

(Multiple Choice)
4.7/5
(41)

If resources are to be considered in planning, it is necessary to

(Multiple Choice)
4.8/5
(42)

  -Resource levelling, or smoothing, is a method for -Resource levelling, or smoothing, is a method for

(Multiple Choice)
4.8/5
(38)

  -Resource levelling, or smoothing, levels the resources so that -Resource levelling, or smoothing, levels the resources so that

(Multiple Choice)
4.8/5
(34)

In addition to showing the technical constraints among activities, how does the network logic also take into account resource constraints?

(Multiple Choice)
4.8/5
(44)
Showing 1 - 20 of 22
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)