The statement, 'Network diagrams illustrate the technical constraints among activities', means the activities are constrained because
A) each of the activities is independent from the other activities.
B) one activity cannot be started until the predecessors are finished.
C) the activities use different resources to be completed.
D) some activities use the same resources that may not be available.
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Given this project and the requirement that
Q10: Given this project and the requirement that
Q13: This example has level resources of three
Q16: Resource utilisation charts based on each activity's
Q17: If resources are to be considered in
Q18: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8900/.jpg" alt=" -Resource levelling, or
Q19: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8900/.jpg" alt=" -Resource levelling, or
Q32: Select which of the following does not
Q36: In addition to showing the technical constraints
Q39: In resource-limited scheduling, the lower priority activities