Exam 3: Developing Project Proposals
Exam 1: Project Management Concepts78 Questions
Exam 2: Identifying and Selecting Projects69 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility and Activity Sequence115 Questions
Exam 5: Developing the Schedule83 Questions
Exam 6: Resource Utilisation22 Questions
Exam 7: Determining Costs, Budget and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project41 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organisational Structures65 Questions
Select questions type
By having a customer supply schedule, the contractor is protected from incurring schedule slippage caused by customer delays in furnishing information, parts, or other items.
Free
(True/False)
4.9/5
(44)
Correct Answer:
True
A contractor bidding on a fixed-price project must develop
Free
(Multiple Choice)
4.9/5
(44)
Correct Answer:
A
Proposals must be realistic in terms of the proposed scope, cost, and schedule in the eyes of the customer.
Free
(True/False)
4.9/5
(43)
Correct Answer:
True
For projects that are new and have high risk, the contractor should include larger amounts of contingency.
(True/False)
4.8/5
(41)
Cost-reimbursement contracts are most appropriate for projects that
(Multiple Choice)
4.8/5
(27)
The proposal should include a lengthy, detailed list of activities to show planning has been well thought out by the contractor.
(True/False)
4.8/5
(32)
Changes can be initiated by the customer or be proposed by the contractor.Some changes may necessitate a change in price (increase or decrease); others may not.
(True/False)
4.9/5
(40)
A good way to start a conversation with a potential customer at XYS Company is
(Multiple Choice)
4.8/5
(42)
A ballpark estimate is acceptable for the proposal.There will be time to figure out the budget after the contract is won.
(True/False)
4.8/5
(37)
A proposal manager is required to have a consistent, comprehensive proposal by the due date in the RFP.
(True/False)
4.7/5
(40)
A complex proposal is a technical report with charts and figures to explain the approach.
(True/False)
4.7/5
(41)
The length of the proposal is not as important as the quality of the information contained in the proposal.
(True/False)
4.8/5
(38)
In a , the customer agrees to pay the contractor for all actual costs (labour, materials, and so on), regardless of amount, plus some agreed-upon profit.
(Multiple Choice)
4.8/5
(30)
A bid/no-bid checklist helps a contractor to decide whether or not to submit a proposal in response to an RFP.
(True/False)
4.9/5
(29)
Contractors should get to know people in customer organisations
(Multiple Choice)
4.7/5
(46)
Contractors interested in submitting a proposal in response to an RFP must be realistic about the probability of being selected as the winning contractor.
(True/False)
4.9/5
(43)
Proposals that promise too much or are overly optimistic may seem believable and support that the contractor understands what needs to be done and how to do it.
(True/False)
4.8/5
(36)
Helping customers identify needs, even if they are needs your company cannot help them address, is a way to position your company to win future contracts.
(True/False)
4.7/5
(39)
Showing 1 - 20 of 112
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)