Exam 3: Developing Project Proposals

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

By having a customer supply schedule, the contractor is protected from incurring schedule slippage caused by customer delays in furnishing information, parts, or other items.

Free
(True/False)
4.9/5
(44)
Correct Answer:
Verified

True

A contractor bidding on a fixed-price project must develop

Free
(Multiple Choice)
4.9/5
(44)
Correct Answer:
Verified

A

Proposals must be realistic in terms of the proposed scope, cost, and schedule in the eyes of the customer.

Free
(True/False)
4.9/5
(43)
Correct Answer:
Verified

True

For projects that are new and have high risk, the contractor should include larger amounts of contingency.

(True/False)
4.8/5
(41)

Cost-reimbursement contracts are most appropriate for projects that

(Multiple Choice)
4.8/5
(27)

The proposal should include a lengthy, detailed list of activities to show planning has been well thought out by the contractor.

(True/False)
4.8/5
(32)

Changes can be initiated by the customer or be proposed by the contractor.Some changes may necessitate a change in price (increase or decrease); others may not.

(True/False)
4.9/5
(40)

A good way to start a conversation with a potential customer at XYS Company is

(Multiple Choice)
4.8/5
(42)

A ballpark estimate is acceptable for the proposal.There will be time to figure out the budget after the contract is won.

(True/False)
4.8/5
(37)

A BAFO requested by a customer is

(Multiple Choice)
4.8/5
(38)

A proposal manager is required to have a consistent, comprehensive proposal by the due date in the RFP.

(True/False)
4.7/5
(40)

A complex proposal is a technical report with charts and figures to explain the approach.

(True/False)
4.7/5
(41)

The length of the proposal is not as important as the quality of the information contained in the proposal.

(True/False)
4.8/5
(38)

In a , the customer agrees to pay the contractor for all actual costs (labour, materials, and so on), regardless of amount, plus some agreed-upon profit.

(Multiple Choice)
4.8/5
(30)

A bid/no-bid checklist helps a contractor to decide whether or not to submit a proposal in response to an RFP.

(True/False)
4.9/5
(29)

Contractors should get to know people in customer organisations

(Multiple Choice)
4.7/5
(46)

Total Rand value approach gives

(Multiple Choice)
4.9/5
(30)

Contractors interested in submitting a proposal in response to an RFP must be realistic about the probability of being selected as the winning contractor.

(True/False)
4.9/5
(43)

Proposals that promise too much or are overly optimistic may seem believable and support that the contractor understands what needs to be done and how to do it.

(True/False)
4.8/5
(36)

Helping customers identify needs, even if they are needs your company cannot help them address, is a way to position your company to win future contracts.

(True/False)
4.7/5
(39)
Showing 1 - 20 of 112
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)