Exam 10: Sizing Pv Systems
Exam 1: Introduction to Photovoltaics20 Questions
Exam 2: Photovoltaic System Installation Safety19 Questions
Exam 3: Understanding Electricity Basics20 Questions
Exam 4: Solar Fundamentals20 Questions
Exam 5: Pv Modules20 Questions
Exam 6: Batteries20 Questions
Exam 7: Charge Controllers20 Questions
Exam 8: Inverters20 Questions
Exam 9: Pv System Wiring and the Nec19 Questions
Exam 10: Sizing Pv Systems20 Questions
Exam 11: Installing Pv Systems20 Questions
Exam 12: Maintaining and Troubleshooting a Pv System20 Questions
Select questions type
The duty cycle is the amount of time that a specific electrical load operates.
Free
(True/False)
4.8/5
(37)
Correct Answer:
True
If the building's loads change significantly over the course of a year, it is acceptable to use the month with lowest insolation as the design month.
Free
(True/False)
4.8/5
(36)
Correct Answer:
False
Where do you start when sizing a PV system?
Free
(Essay)
4.8/5
(36)
Correct Answer:
When sizing a PV system, you start by determining the electrical load.
In a standard charge controller, all of the system components have the same voltage.
(True/False)
4.8/5
(30)
Explain the Energy Star label, where it originated, and what it means.
(Essay)
4.8/5
(42)
The ____________________ electric energy usage can be found on a building's electric utility bill, or the building owner can contact the local electric utility.
(Short Answer)
4.9/5
(33)
The use of an MPPT and/or step down charge controller in a stand-alone PV system requires the array to be sized a little differently than when using a(n) ____________________ charge controller.
(Short Answer)
4.9/5
(39)
Sizing a(n) ____________________ PV system is simpler than sizing a stand-alone PV system primarily because there are not as many system components to determine.
(Short Answer)
4.9/5
(37)
The rule of thumb often used to calculate the surge load is to simply multiply the required watts of a load by ____________________.
(Short Answer)
4.8/5
(39)
What is the overall process for determining inverter size for a stand-alone PV system?
(Essay)
4.8/5
(49)
For the lowest temperature termination rating, assume that all terminations are rated ___________________°C unless you know for sure that there are 60°C or 90°C terminations in the circuit.
(Short Answer)
4.8/5
(41)
A phantom load is a load type that draws a large amount of current, even when the load is "OFF".
(True/False)
4.8/5
(39)
What is the one major difference between a bimodal PV system and a stand-alone PV system?
(Essay)
4.8/5
(36)
Why should a grid-tie PV system not be sized larger than needed for the building's average annual electrical load?
(Essay)
4.9/5
(33)
Sizing the wire from the inverter to the AC loadcenter in a grid-tie PV system is sized the same way as sizing the wire run from a(n) ___________________ to an AC loadcenter in a stand-alone PV system.
(Short Answer)
4.8/5
(41)
A(n) ____________________ PV system needs to be sized so that it can supply the total electrical load of the building it serves.
(Short Answer)
4.8/5
(39)
The system loss ___________________ factor takes into account the types of losses that occur when converting the PV array produced DC electricity to AC electricity.
(Short Answer)
4.9/5
(41)
Explain how output power rating is used to determine the number of inverters needed in a grid-tie PV system.
(Essay)
4.9/5
(40)
Load ____________________ is the process of changing large electrical loads in a building to another form of power such as natural gas or propane.
(Short Answer)
4.9/5
(34)
A common assumption in most stand-alone PV system installations is that the wiring from module to module and from the array modules to the combiner box is the same size as the wire leads that were installed on the PV modules by the manufacturer.
(True/False)
4.9/5
(43)
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)