Exam 12: Pricing Masonry, Carpentry and Finishes Work
Exam 1: Introduction20 Questions
Exam 2: The Estimating Process and Preliminary Procedures20 Questions
Exam 3: Measuring Quantities Generally20 Questions
Exam 4: Measuring Sitework, Excavation and Piling20 Questions
Exam 5: Measuring Concrete Work20 Questions
Exam 6: Measuring Masonry Work20 Questions
Exam 7: Measuring Carpentry and Miscellaneous Items20 Questions
Exam 8: Pricing Generally20 Questions
Exam 9: Pricing Construction Equipment20 Questions
Exam 10: Pricing Excavation and Backfill20 Questions
Exam 11: Pricing Concrete Work20 Questions
Exam 12: Pricing Masonry, Carpentry and Finishes Work20 Questions
Exam 13: Pricing Subcontractors Work20 Questions
Exam 14: Pricing General Expenses20 Questions
Exam 15: Closing the Bid20 Questions
Exam 16: Budget Estimating20 Questions
Exam 17: Elemental Estimating20 Questions
Exam 18: Life-Cycle Costing20 Questions
Select questions type
In the residential industry especially, a subcontractor will offer to perform carpentry framing work at a ____ of building area.
Free
(Multiple Choice)
4.7/5
(35)
Correct Answer:
D
A ____% allowance for waste is considered appropriate on finish carpentry materials.
Free
(Multiple Choice)
4.9/5
(35)
Correct Answer:
C
Lumber is graded according to all of the following categories EXCEPT _____________.
Free
(Multiple Choice)
4.7/5
(34)
Correct Answer:
C
Factory and ____ lumber is lumber selected for remanufacturing use.
(Multiple Choice)
4.8/5
(25)
Hardware for rough carpentry, including nails and other fastening devices, is usually priced as a percentage of the price for lumber.
(True/False)
4.9/5
(35)
The amount of nails required for rough carpentry can be roughly determined by allowing ____ lbs of nails for every 1000 board feet of lumber.
(Multiple Choice)
4.7/5
(39)
Higher outputs can be expected when constructing columns, pilasters, and curved work rather than long lengths of plain walls.
(True/False)
4.9/5
(31)
Material prices are determined from suppliers who are required to quote prices to supply and deliver items that meet specifications.
(True/False)
4.8/5
(35)
Hand tools and some crane time for unloading and hoisting are seldom required with the installation of finish carpentry.
(True/False)
4.8/5
(30)
____ hardware for lumber mostly consists of nails, but other fasteners and such items as joist hangers may also be required.
(Multiple Choice)
4.7/5
(28)
Fabricating and installing roof components such as hips, valleys, ridges, and rafters require far more time than fabricating and installing plain joists.
(True/False)
4.9/5
(30)
The amount of nails required for rough carpentry can be roughly determined by allowing ____ lbs of nails for every 1000 square feet of sheathing.
(Multiple Choice)
4.9/5
(40)
The price of masonry bricks and blocks varies over a wide range depending on the size, type, and color of units required.
(True/False)
4.7/5
(39)
Allowable stresses are specified according to ____ of lumber and grade within each of the categories.
(Multiple Choice)
4.9/5
(46)
Which of the following is NOT considered a job factor that influences the price of rough carpentry?
(Multiple Choice)
4.8/5
(29)
Lumber is generally available in lengths that are multiples of ____ feet.
(Multiple Choice)
4.8/5
(34)
The size of lumber is stated in accordance with its __________ size.
(Multiple Choice)
4.7/5
(33)
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)