Exam 15: Closing the Bid
Exam 1: Introduction20 Questions
Exam 2: The Estimating Process and Preliminary Procedures20 Questions
Exam 3: Measuring Quantities Generally20 Questions
Exam 4: Measuring Sitework, Excavation and Piling20 Questions
Exam 5: Measuring Concrete Work20 Questions
Exam 6: Measuring Masonry Work20 Questions
Exam 7: Measuring Carpentry and Miscellaneous Items20 Questions
Exam 8: Pricing Generally20 Questions
Exam 9: Pricing Construction Equipment20 Questions
Exam 10: Pricing Excavation and Backfill20 Questions
Exam 11: Pricing Concrete Work20 Questions
Exam 12: Pricing Masonry, Carpentry and Finishes Work20 Questions
Exam 13: Pricing Subcontractors Work20 Questions
Exam 14: Pricing General Expenses20 Questions
Exam 15: Closing the Bid20 Questions
Exam 16: Budget Estimating20 Questions
Exam 17: Elemental Estimating20 Questions
Exam 18: Life-Cycle Costing20 Questions
Select questions type
Whereas lump-sum bids involve calculating a single final price and assembling a list of subtrades, with a unit-price bid, the contractor is also required to complete a "_______", that is, an itemized breakdown of the work of the project.
Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
D
The bid markup has one main component: profit.
Free
(True/False)
4.8/5
(28)
Correct Answer:
False
A construction contract bid is compiled in three stages: the advance stage, the review stage, and the ____ stage.
Free
(Multiple Choice)
4.8/5
(24)
Correct Answer:
D
A construction bid contract is compiled in three stages which include all of the following EXCEPT the _____ stage.
(Multiple Choice)
4.8/5
(24)
The last stage in the preparation of a unit-price bid is to ____.
(Multiple Choice)
4.9/5
(37)
The recap format for the takeoff items of a unit- price bid is the same as the format used with a lump-sum bid.
(True/False)
4.9/5
(29)
The first step in the cost control process is assembling cost data for use in estimating future jobs.
(True/False)
4.9/5
(35)
The ____ function in a construction company will record all the expenses incurred in the operation of the entire company.
(Multiple Choice)
4.9/5
(36)
Most contractors use a ____ sheet to gather together all of the constituent prices of the estimate.
(Multiple Choice)
5.0/5
(29)
Contractors seldom see an advantage in allowing a higher proportion of overheads and fee against the work being completed early in the project.
(True/False)
4.9/5
(34)
At the very start of the estimating process, the estimator can set up the summary sheet by checking off the trades that will be completed by "own forces" and those that will be subcontracted.
(True/False)
4.9/5
(27)
Add-ons for small tools and payroll additives are calculated as a percentage of the total labor amount of the bid.
(True/False)
4.8/5
(34)
The information on a ____ is generally requested to provide a basis for evaluating monthly progress payments on the project.
(Multiple Choice)
4.9/5
(42)
In the bid markup, profit is generally assessed as a compensation for the risk taken by the contractor.
(True/False)
4.7/5
(26)
____ is defined as the amount of money remaining after all project expenses and company expenses have been paid.
(Multiple Choice)
4.8/5
(34)
Most contractors use a standard format of summary to capture all the main components of an estimate.
(True/False)
5.0/5
(30)
A stipulated sum of money to be expended by a contractor on a specific work item on a project is usually referred to as a ____.
(Multiple Choice)
4.8/5
(35)
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)