Exam 17: Elemental Estimating
Exam 1: Introduction20 Questions
Exam 2: The Estimating Process and Preliminary Procedures20 Questions
Exam 3: Measuring Quantities Generally20 Questions
Exam 4: Measuring Sitework, Excavation and Piling20 Questions
Exam 5: Measuring Concrete Work20 Questions
Exam 6: Measuring Masonry Work20 Questions
Exam 7: Measuring Carpentry and Miscellaneous Items20 Questions
Exam 8: Pricing Generally20 Questions
Exam 9: Pricing Construction Equipment20 Questions
Exam 10: Pricing Excavation and Backfill20 Questions
Exam 11: Pricing Concrete Work20 Questions
Exam 12: Pricing Masonry, Carpentry and Finishes Work20 Questions
Exam 13: Pricing Subcontractors Work20 Questions
Exam 14: Pricing General Expenses20 Questions
Exam 15: Closing the Bid20 Questions
Exam 16: Budget Estimating20 Questions
Exam 17: Elemental Estimating20 Questions
Exam 18: Life-Cycle Costing20 Questions
Select questions type
The ____ UniFormat is a function-based elemental breakdown that provides what is needed for an elemental estimating system.
Free
(Multiple Choice)
4.9/5
(32)
Correct Answer:
B
To better achieve the cost control required throughout the design phase of a project, the single price estimate needs to be broken down into its constituent parts.
Free
(True/False)
4.8/5
(43)
Correct Answer:
True
The main uses of elemental analysis include all of the following EXCEPT ________.
Free
(Multiple Choice)
4.7/5
(34)
Correct Answer:
A
Very little information is required about a new project to prepare an estimate using ____ analysis.
(Multiple Choice)
4.7/5
(39)
The basic unit of the UniFormat breakdown is the building element that is defined as a major component of most buildings that performs the same function in the building.
(True/False)
4.7/5
(36)
When a developer first considers the idea of a project, he may quickly calculate the anticipated cost of the work using a ____ estimate.
(Multiple Choice)
4.7/5
(28)
The objective of ____ analysis is to provide a consistent reference format for the evaluation, estimation, and tracking of construction costs throughout the life of a project-from feasibility through occupancy and use to eventual demolition.
(Multiple Choice)
4.9/5
(37)
An element represents a component that always performs the same function in a building.
(True/False)
4.9/5
(35)
The ____ contingency is an amount that is added to the cost estimate which reflects the price increases that are anticipated over the time between the date of the analysis being used and the time when the new project is constructed.
(Multiple Choice)
5.0/5
(35)
All that is required to prepare a quick and accurate elemental estimate is the basic size and shape of the building and its use and location, as well as historical cost data of similar buildings constructed at the same general location.
(True/False)
4.9/5
(29)
The ____ is obtained by dividing the quantity of the element by the gross floor area of the project.
(Multiple Choice)
4.9/5
(33)
Three contingencies are usually applied to an elemental estimate at the conceptual stage. They include all of the following EXCEPT __________.
(Multiple Choice)
4.8/5
(34)
In order to obtain a realistic assessment of the cost of construction, a ____ estimate should be used.
(Multiple Choice)
5.0/5
(38)
When using an elemental analysis as an estimating tool, the ratio can be used to check for design errors.
(True/False)
4.7/5
(34)
The ____ is the cost of the element divided by its quantity.
(Multiple Choice)
4.9/5
(39)
A trade breakdown is not detailed enough for the preliminary type of estimate prepared at the conception stage of a project.
(True/False)
4.9/5
(39)
Elemental analysis furnishes less useful information than the one budget price that results from a single-rate estimate.
(True/False)
5.0/5
(35)
An elemental cost analysis of a finished project can be likened to an estimate in reverse.
(True/False)
4.9/5
(39)
Ratios can help explain why one building is more expensive than another.
(True/False)
4.8/5
(33)
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)