Exam 3: Product and Process Design and Mapping
Exam 1: Introduction to Supply Chain and Operations Management67 Questions
Exam 2: Supply Chain and Operations Strategy80 Questions
Exam 3: Product and Process Design and Mapping89 Questions
Exam 4: Service Design96 Questions
Exam 5: Customer Relationship Management52 Questions
Exam 6: Strategic Sourcing78 Questions
Exam 7: Supplier Management59 Questions
Exam 8: Demand Management and Forecasting75 Questions
Exam 9: Inventory Management Fundamentals and Independent Demand84 Questions
Exam 10: Sales and Operations Planning and Enterprise Resource Planning110 Questions
Exam 11: Logistics94 Questions
Exam 12: Project Management90 Questions
Exam 13: Supply Chain Quality Management84 Questions
Exam 14: Statistical Process Control74 Questions
Exam 15: Lean and Six Sigma Management and Leading Change76 Questions
Select questions type
A method for translating customer requirements into functional design is known as ________.
(Short Answer)
4.8/5
(38)
Use the information below to answer the following question(s).
A small automotive parts manufacture is evaluating opening a new manufacturing plant for assembly of its battery chargers line. The location being considered has a monthly fixed cost of $42,000 and a variable cost of $3 per charger. Chargers sell for $ 7 each.
-What is the break-even point in units per month?
(Multiple Choice)
4.9/5
(43)
In concurrent engineering,the different tasks of design are performed ________.
(Short Answer)
4.7/5
(35)
The process which is most capital-intensive and often requires very specialized technology is ________.
(Short Answer)
4.8/5
(33)
Goods that use similar technologies that can coexist in a family of products are known as ________.
(Short Answer)
4.8/5
(39)
The process of allocating tasks to process workstations in an efficient manner is called
(Multiple Choice)
4.8/5
(27)
Use the information below to answer the following question(s).
A production line operates for 450 minutes per day. Desired production volume is 80 units per day. Total task time to make the product is 56 minutes.
-What is the minimum number of workstations required?
(Multiple Choice)
4.7/5
(33)
The selection and implementation of methods for producing products is known as ________.
(Short Answer)
4.8/5
(31)
In a process map,the diamond symbol indicates that work is actually performed.
(True/False)
4.9/5
(36)
The process of allocating tasks to process workstations in an efficient manner is called ________.
(Short Answer)
4.8/5
(39)
A manufacturer of video game consoles introduces a new product in the market with new eye sensor technology.This is an example of which kind of R&D?
(Multiple Choice)
4.9/5
(37)
Continuous-flow processes are capital-intensive usually requiring very specialized technologies.
(True/False)
4.8/5
(32)
The tool used to compare various process options and their relationship to volume and variety is known as ________.
(Short Answer)
4.9/5
(25)
The process which is used to produce a variety of products in low volumes is ________.
(Short Answer)
4.8/5
(32)
The minimum possible cycle time in a production line is determined by the
(Multiple Choice)
4.8/5
(27)
Showing 21 - 40 of 89
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)