Exam 5: Different Construction Contract Delivery Methods
Specialty Contractors are sometimes required to install equipment to meet a certain level of performance
True
Using complete sentences, describe in full the construction contract delivery methods. Be very careful to provide the distinguishing characteristics of each.
There are several construction contract delivery methods, each with its own distinguishing characteristics. The first method is the traditional design-bid-build method, where the owner contracts separately with a designer and a contractor. This method allows for a clear separation of design and construction responsibilities, but can lead to potential conflicts between the designer and contractor.
The second method is the design-build method, where the owner contracts with a single entity that is responsible for both the design and construction of the project. This method allows for a single point of responsibility and can lead to faster project delivery, but may limit the owner's control over the design process.
The third method is the construction manager at risk method, where the owner contracts with a construction manager who is responsible for managing the construction process and guaranteeing the project's cost and schedule. This method allows for early contractor involvement and can lead to better cost control, but may result in increased project costs due to the construction manager's fee.
The fourth method is the integrated project delivery method, where the owner contracts with a team of key project participants, including the designer, contractor, and other stakeholders, to collaboratively work together from the project's inception to completion. This method allows for increased collaboration and can lead to improved project outcomes, but may require a higher level of trust and communication among all parties involved.
Overall, each construction contract delivery method has its own unique characteristics and considerations, and the choice of method should be carefully considered based on the specific needs and goals of the project.
The best part about Design-Bid-Build is it does not create an adversarial atmosphere
Multi-prime Contracting is most often used by public Owners, such as School Boards
The expertise of each party is to be shared in an IPD relationship
In Design-Bid-Build, the Owner usually has a good idea of the final price for the project
A special purpose vehicle is created specifically for executing a PPP project
Since the Design Builder is liable for all design ambiguities and defect, there is less arguing and fault-finding and more solutions come forth quicker
In Design-Bid-Build, the roles of the parties overlap and even duplicate each other so it is easier to complete the work