Exam 12: Differing Site Conditions
Exam 1: Getting Started18 Questions
Exam 2: An Introduction to Contracts, Torts, Statutes and Regulations22 Questions
Exam 3: Owners, Designers, and Constructors20 Questions
Exam 4: The Basics of Construction Contracts24 Questions
Exam 5: Different Construction Contract Delivery Methods23 Questions
Exam 6: Interpreting the Contract38 Questions
Exam 7: Killer Clauses26 Questions
Exam 8: Insurance23 Questions
Exam 9: Bonds17 Questions
Exam 10: Warranties11 Questions
Exam 11: Getting Started20 Questions
Exam 12: Differing Site Conditions14 Questions
Exam 13: Schedule21 Questions
Exam 14: Liens12 Questions
Select questions type
With a Differing Site Condition, the Contract Administrator should
Free
(Multiple Choice)
4.9/5
(31)
Correct Answer:
D
A Type I Differing Site Condition is when actual conditions are not what was indicated on the drawings
Free
(True/False)
4.8/5
(41)
Correct Answer:
True
Reliance upon the Spearin Doctrine is sufficient for relief from Differing Site Conditions
Free
(True/False)
4.9/5
(42)
Correct Answer:
False
If there is an exculpatory clause protecting the Owner, key for the Contractor in resolving a Differing Site Condition favorably will be
(Multiple Choice)
4.8/5
(35)
Differing Site Conditions usually refers to something unexpected underground, but it does not have to be so
(True/False)
4.9/5
(32)
Through an exculpatory clause, an Owner will place responsibility on the Contractor for actions caused by the Owner's agents
(True/False)
4.9/5
(37)
A Type II Differing Site Condition is what no one would have expected to exist without regard to what was indicated on the drawings
(True/False)
4.8/5
(32)