The Measured Mile approach utilizes costs per unit put in place incurred during a specific time in the project when production should be appropriate for that unit

Free
(True/False)
4.8/5
(35)
Correct Answer:
Verified

True

Fast tracking is one method to shorten a schedule

Free
(True/False)
4.8/5
(38)
Correct Answer:
Verified

True

Characteristic of a Critical Path Schedule is

Free
(Multiple Choice)
4.9/5
(21)
Correct Answer:
Verified

A

Ambiguities will always be ""construed against the drafter"" of the documents containing the ambiguity

(True/False)
4.7/5
(33)

Without a change order clause in the Contract

(Multiple Choice)
4.8/5
(34)

If a change affects the schedule

(Multiple Choice)
4.8/5
(45)

Constructive changes

(Multiple Choice)
5.0/5
(37)

A Patent Ambiguity is one that no one could have anticipated

(True/False)
4.7/5
(41)

Float on the critical path gives everyone a chance to catch up with the project schedule

(True/False)
4.9/5
(36)

The Eichleay formula was developed for

(Multiple Choice)
4.9/5
(42)

Fortunately, Constructive Acceleration guarantees the Contractor will be compensated for additional costs related to extra work required to meet the original schedule

(True/False)
4.9/5
(43)

Constructive changes can seemingly be clarification of the intended work, but they can lead to additional costs

(True/False)
4.9/5
(34)

In most cases, the Contract Administrator has to recognize that finding fault is not finding a solution

(True/False)
4.8/5
(29)

Until one knows otherwise

(Multiple Choice)
4.7/5
(35)

The Eichleay formula is used to determine field overhead

(True/False)
4.9/5
(33)

The ""Measured Mile""

(Multiple Choice)
4.9/5
(45)

Sometimes the requirements of proof and detail are so burdensome that a small change does not pay for itself

(True/False)
4.8/5
(39)

In most cases, a flaw or ambiguity in the Contract documents

(Multiple Choice)
4.8/5
(46)

The Owner can grant to an agent the authority to make changes

(True/False)
4.8/5
(47)

Directed Acceleration will be compensated for once the costs are determined

(True/False)
4.9/5
(40)