In arrow notation, the longer the arrow, the longer the activity's duration.

Free
(True/False)
4.8/5
(41)
Correct Answer:
Verified

False

Which of the following is not true about network schedules?

Free
(Multiple Choice)
4.8/5
(42)
Correct Answer:
Verified

D

  -What is the early start day for the Form/Conc. 2 activity? -What is the early start day for the Form/Conc. 2 activity?

Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
Verified

D

   -What is the late finish time for activity  35-45  ? -What is the late finish time for activity 354535-45 ?

(Multiple Choice)
4.9/5
(41)

  -What is the project's duration? -What is the project's duration?

(Multiple Choice)
4.8/5
(37)

   -What is the correct  i-j  notation for the Cure 1 activity? -What is the correct iji-j notation for the Cure 1 activity?

(Multiple Choice)
4.9/5
(35)

A network schedule shows ????.

(Multiple Choice)
4.9/5
(42)

A network schedule is continuous.

(True/False)
4.8/5
(43)

Project schedules are necessary tools to control the ????component of a construction project.

(Multiple Choice)
4.9/5
(32)

  -What is the early finish time for Set Base Plates 2? -What is the early finish time for Set Base Plates 2?

(Multiple Choice)
4.8/5
(32)