Exam 5: Project Chronology

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

In which of the following are the four stages of design in the correct order?

Free
(Multiple Choice)
4.8/5
(41)
Correct Answer:
Verified

B

Matching Identify in which project phase the following work would occur. -Store spare parts and collect warranties

Free
(Multiple Choice)
4.9/5
(29)
Correct Answer:
Verified

E

Matching Identify in which project phase the following work would occur. -Write project specifications

Free
(Multiple Choice)
4.9/5
(41)
Correct Answer:
Verified

B

Matching Identify in which project phase the following work would occur. -Broad-scale planning

(Multiple Choice)
4.9/5
(32)

Matching Identify in which project phase the following work would occur. -Contract for subcontract services

(Multiple Choice)
4.9/5
(45)

Long-lead items are materials or equipment typically ordered and bought by the in advance of the contract award.

(Multiple Choice)
4.9/5
(39)

Matching Identify in which project phase the following work would occur. -Coordinate labor and material installation

(Multiple Choice)
4.8/5
(30)

With the cost of money increasing 10 percent per year, a dollar spent on construction today is worth more than a dollar earned two years in the future.

(True/False)
4.7/5
(36)

As a project moves through the design phase, decisions and details considered become more numerous, and of a smaller scale.

(True/False)
4.8/5
(33)

Assuming no contract changes, during which of the following project stages is the actual cost of construction most likely to be determined?

(Multiple Choice)
4.7/5
(46)