Milestones are not depended upon the predecessor activities in the project plan.

(True/False)
4.7/5
(30)

A diagram of nodes connected by directional arcs that defines the project and illustrates the technical of all activities is referred to as a network.

(True/False)
4.8/5
(34)

Explain why the term "critical path" has less meaning in cases where the activity times are not known with certainty.

(Not Answered)
This question doesn't have any answer yet
Ask our community

A big advantage of AON networks is that they are easier to draw.

(True/False)
4.9/5
(42)

The amount of time a noncritical task can be delayed without delaying the project is called?

(Multiple Choice)
4.7/5
(27)

Networks are usually drawn with a "Start" node to the right and a "Finish" node to the left.

(True/False)
4.9/5
(39)

If task duration estimates are carefully made, the project manager needs to only examine the critical path when conducting a risk analysis.

(True/False)
4.9/5
(49)

The actual project duration will be known with certainty after the project is completed.

(True/False)
4.9/5
(34)

"Merger" is a term used to describe the situation in which two or more paths in a network join together.

(True/False)
4.8/5
(37)

What is a merger and what problems do mergers create?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Why is it necessary for the PM to be aware and to manage the slack in the project?

(Short Answer)
4.8/5
(38)

What is project slack?

(Multiple Choice)
4.8/5
(32)

A disadvantage of Gantt charts is that they are hard to draw.

(True/False)
4.7/5
(40)

What is the standard deviation of a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively assuming the estimates were made at the 99% plus level?

(Multiple Choice)
4.8/5
(28)

A situation where two or more activities have the same starting and finishing nodes or where a single activity connects to two or more nodes is called a dummy task

(True/False)
4.8/5
(40)

When it was originally developed, PERT used certain (deterministic) methods to estimate activity duration.

(True/False)
4.8/5
(33)

To manage a project successfully, the project manager need only pay close attention to tasks on the critical path.

(True/False)
4.8/5
(38)

A Term not used in the discussion of PERT/CPM analysis is

(Multiple Choice)
4.9/5
(45)

What is activity slack?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Float refers to the amount of time a noncritical task can be delayed without causing a delay in the entire project.

(True/False)
4.8/5
(26)