The shortest time to complete a network is equal to the duration of the longest path through the network.

(True/False)
4.8/5
(40)

Which of the following linkages is used to start two or more activities at the same time?

(Multiple Choice)
4.9/5
(35)

The amount of time an activity can be delayed without affecting the start time of any successor activity is known as free slack.

(True/False)
4.9/5
(34)