Activities that have duration but do not require resources are referred to as pseudoactivities.
(True/False)
4.8/5
(34)
A project that must be completed with in the specified performance requirements is considered…
(Multiple Choice)
4.8/5
(40)
Which of the following rules maximizes the number of tasks that can be completed by a system in a given period of time?
(Multiple Choice)
5.0/5
(36)
A limitation associated with traditional approaches to project management is that the dependency between resources and tasks is often ignored.
(True/False)
4.8/5
(27)
Applying "line balancing" techniques to balance the capacity of a project typically yields significant benefits.
(True/False)
4.8/5
(33)
Pools of like workers are most useful when labor is subdivided into highly specialized subtasks.
(True/False)
4.9/5
(38)
Explain the concept of a project buffer.
(Not Answered)
This question doesn't have any answer yet
Which of the following priority rules makes resources available so that activities start on their LSTs whenever possible without increasing the project's duration?
(Multiple Choice)
4.7/5
(35)
Explain how the commonly made assumption of known activity times can lead to unrealistic project deadlines.
(Not Answered)
This question doesn't have any answer yet
To crash a project, which of the following principles apply? 1) Focus on the critical path(s) when trying to shorten the duration of a project, 2) Select the least expensive way to do it 3) Crash non-critical activities
(Multiple Choice)
4.7/5
(51)
Explain the concept of a feeding buffer.
(Not Answered)
This question doesn't have any answer yet
The process of line balancing is when individual production lines are made to generate the required amount of product with a little excess capacity as possible.
(True/False)
4.8/5
(35)
Often it is beneficial to crash activities not on the critical path.
(True/False)
4.9/5
(30)
The task duration with standard-practice resource usage is referred to as the…
(Multiple Choice)
4.9/5
(35)
It is considered good management to crash the least costly activities before the more costly ones.
(True/False)
4.9/5
(43)
What is resource leveling? Why is it needed?
(Not Answered)
This question doesn't have any answer yet
When the work is routine, fast-tracking rarely causes serious problems.
(True/False)
4.9/5
(39)
What is resource loading?
(Not Answered)
This question doesn't have any answer yet
A project that must be completed by a fixed time is referred to as resource constrained.
(True/False)
4.8/5
(37)