Exam 8: Closing Projects and Best Practices
Exam 1: An Introduction to Project, program, and Portfolio Management75 Questions
Exam 2: Project, program, and Portfolio Selection75 Questions
Exam 3: Initiating Projects75 Questions
Exam 4: Planning Projects, part I Project Integration, scope, time, and Cost Management100 Questions
Exam 5: Planning Projects, part 2 Project Quality, human Resource, communications, risk, and Procurement Management92 Questions
Exam 6: Executing Projects96 Questions
Exam 7: Monitoring and Controlling Projects90 Questions
Exam 8: Closing Projects and Best Practices50 Questions
Select questions type
Every project should have procedures to guide closure.
Free
(True/False)
4.8/5
(30)
Correct Answer:
True
Organizations should strive to improve all their business processes,including procurement management.
Free
(True/False)
4.9/5
(43)
Correct Answer:
True
The ____________________ Baseline Study provides a comprehensive overview of project management practices in organizations and industries worldwide,with over 600 participants.
Free
(Short Answer)
4.8/5
(47)
Correct Answer:
Organizational Project Management
OPM
Organizational Project Management (OPM)
OPM (Organizational Project Management)
The last task in project integration management is ____________________ the project.
(Short Answer)
4.9/5
(41)
____________________ closure procedures should define the approval process for all project deliverables.
(Short Answer)
4.8/5
(36)
Outputs from ____ closure include updates to organizational process assets and closed contracts.
(Multiple Choice)
4.9/5
(34)
____ audits are often performed during contract closure to identify lessons learned in the entire procurement process.
(Multiple Choice)
4.9/5
(29)
Which of the following is a category under project best practices?
(Multiple Choice)
4.8/5
(32)
OPM3 defines ____________________ project management as "the systematic management of projects,programs,and portfolios in alignment with the achievement of strategic goals."
(Short Answer)
4.7/5
(29)
A(n)____________________ model is a framework for helping organizations improve their processes and systems.
(Short Answer)
4.9/5
(36)
To prevent problems and improve project management,many people are attempting to discover and use best practices,such as developing more realistic estimates and forecasts.
(True/False)
4.9/5
(28)
OPM3 is a standard developed to provide a way for organizations to measure their organizational project management maturity against a comprehensive set of best practices.
(True/False)
4.8/5
(28)
When developing a ____ plan,the project team should work with managers in affected operating departments,and the contents of the plan should be tailored to fit the support needs of the project.
(Multiple Choice)
4.8/5
(35)
Best practices are organized into three levels: project,program,and ____.
(Multiple Choice)
4.7/5
(37)
The contract itself should exclude requirements for formal acceptance and closure.
(True/False)
4.9/5
(34)
According to Robert Butrick,you should only engage stakeholders in the last stage of a project.
(True/False)
4.9/5
(32)
Closing projects involves gaining ____ acceptance of the final products and services,and bringing the project to an orderly end.
(Multiple Choice)
4.8/5
(36)
A(n)____ management system provides the ability to easily organize,find,and archive procurement-related documents.
(Multiple Choice)
4.9/5
(28)