Updating the risk register is an optional part of project monitoring and control.

Free
(True/False)
4.8/5
(36)
Correct Answer:
Verified

False

Earned value management involves calculating ____ values for each activity or summary activity from a project's WBS.

Free
(Multiple Choice)
5.0/5
(29)
Correct Answer:
Verified

A

The main communications management tasks performed as part of monitoring and controlling include performance reporting and managing ____________________.

Free
(Short Answer)
4.7/5
(47)
Correct Answer:
Verified

stakeholders

The main monitoring and controlling tasks performed as part of project ____ management include monitoring and controlling project work and performing integrated change control.

(Multiple Choice)
4.9/5
(35)

The key outputs resulting from scope verification and scope control are deliverables that are accepted by the customer.

(True/False)
4.8/5
(35)

The main monitoring and controlling task performed as part of project time management is ____ control.

(Multiple Choice)
4.8/5
(46)

A(n)____ chart displays the history and pattern of variation of a process over time.

(Multiple Choice)
4.8/5
(37)

Performance reporting keeps stakeholders informed about how resources are being used to achieve project objectives.

(True/False)
4.8/5
(42)

Few projects are completed without any conflict.

(True/False)
4.8/5
(30)

If you do not have a good baseline or actual scope,time,and cost information,you cannot use earned value management.

(True/False)
4.8/5
(32)

A(n)____________________ milestone refers to a milestone activity that was actually completed later than originally planned.

(Short Answer)
4.9/5
(32)

____________________ are graphic displays of the logic and flow of processes that help you analyze how problems occur and how processes can be improved.

(Short Answer)
4.9/5
(34)

In the context of monitoring and controlling tasks for project quality management,____ decisions determine if the products or services produced as part of the project will be accepted or rejected.

(Multiple Choice)
4.9/5
(31)

In the columns to the left of the tracking Gantt chart,you can display baseline and actual start and finish dates.

(True/False)
4.8/5
(37)

____________________ change control involves identifying,evaluating,and managing changes throughout the project's life cycle.

(Short Answer)
4.9/5
(35)

____ reports describe where the project stands at a specific point in time.

(Multiple Choice)
4.9/5
(35)

Risk reassessment,risk audits,variance and trend analysis,technical performance measurements,reserve analysis,and status meetings or periodic risk reviews are all tools and techniques for performing ____ monitoring and control.

(Multiple Choice)
4.9/5
(34)

A(n)____________________ is a bar graph of a distribution of variables.

(Short Answer)
4.8/5
(40)

How did Northwest Airlines successfully control the scope of a project to develop a new reservation system?

(Essay)
4.8/5
(41)

Two key outputs of performance reporting are performance reports and ____.

(Multiple Choice)
4.9/5
(30)