Exam 17: Acquiring and Implementing Accounting Information Systems
Exam 1: Introduction to Accounting Information Systems122 Questions
Exam 2: Enterprise Systems141 Questions
Exam 3: Electronic Business E-Business Systems122 Questions
Exam 4: Documenting Information Systems129 Questions
Exam 5: Database Management Systems175 Questions
Exam 6: Relational Databases and SQL103 Questions
Exam 7: Controlling Information Systems: Introduction to Enterprise Risk Management and Internal Control161 Questions
Exam 8: Controlling Information Systems: Introduction to Pervasive Controls159 Questions
Exam 9: Controlling Information Systems: Business Process and Application Controls135 Questions
Exam 10: The Order Entrysales Oes Process134 Questions
Exam 11: The Billingaccounts Receivablecash Receipts Barcr Process134 Questions
Exam 12: The Purchasing Process141 Questions
Exam 13: The Accounts Payablecash Disbursements Apcd Process118 Questions
Exam 14: The Human Resources Process HR Management and Payroll Processes121 Questions
Exam 15: Integrated Production Processes IPP118 Questions
Exam 16: The General Ledger and Business Reporting GLBR Process107 Questions
Exam 17: Acquiring and Implementing Accounting Information Systems206 Questions
Select questions type
The ______________________________ approach forces the users to learn the new system because the old system is not available to fall back on.
(Short Answer)
4.8/5
(33)
The following picture from the text illustrates the ____ approach to systems implementation: 

(Multiple Choice)
4.7/5
(33)
Outsourcing is a term that describes an organization's assigning any of its internal functions (e.g., accounting, legal, or IT) to an outside vendor.
(True/False)
4.9/5
(41)
Similar to the developer of an industrial park, an organization's management or IT steering committee approves a systems development project for further systems development.
(True/False)
4.7/5
(38)
Intangible benefits are those that cannot be reasonably quantified, such as those that result from having improved information.
(True/False)
4.7/5
(39)
After the conversion is completed, the systems development project team writes the project completion report.
(True/False)
4.8/5
(32)
Insurance on a computer installation is an example of a(n) ____ cost.
(Multiple Choice)
4.7/5
(39)
If a new payroll system is installed for the employees of plant 1 at time A, followed by plant 2 at time B, and finally plant 3 at time C, this is an example of the ____ approach to systems implementation.
(Multiple Choice)
4.9/5
(36)
A problem has a(n) ______________________________ feasible solution if it can be solved with existing technology.
(Short Answer)
4.9/5
(36)
One task of the ______________________________ phase is to convert to the new or revised system.
(Short Answer)
4.8/5
(41)
As an internal auditor the accountant could be called in to complete the design, help prepare the contracts, or help plan, conduct, and evaluate the system tests.
(True/False)
4.9/5
(36)
As an analyst, the accountant could be the development team member who conducts a preliminary survey.
(True/False)
4.9/5
(31)
A representative workload, processed on a vendor's proposed system configuration, to obtain comparative throughput measures is called a(n):
(Multiple Choice)
4.9/5
(47)
The user, the programmer, and another member of the programming team do a(n) ______________________________ of the module specifications and the test plan to determine that the test plan is adequate; then the programmer codes the program.
(Short Answer)
4.9/5
(40)
The direct approach is also known as the "big bang" or "cold turkey" approach.
(True/False)
4.9/5
(42)
The logical specification, physical requirements, and budget and schedule are all part of the systems analysis deliverable called a(n) ______________________________.
(Short Answer)
4.8/5
(26)
After the analysis team studies and documents the current physical system they should next:
(Multiple Choice)
4.9/5
(39)
It is always better to develop a system in-house than it is to purchase a standard package.
(True/False)
4.9/5
(36)
After defining the requirements for the new system, the current logical DFD should be modified to reflect the components of the future system. The development team may propose logical design alternatives for the future logical system that may involve derivatives of the following except:
(Multiple Choice)
4.9/5
(46)
Which of the following is a characteristic of external hardware sources?
(Multiple Choice)
4.9/5
(31)
Showing 81 - 100 of 206
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)