Exam 17: Acquiring and Implementing Accounting Information Systems
Exam 1: Introduction to Accounting Information Systems122 Questions
Exam 2: Enterprise Systems141 Questions
Exam 3: Electronic Business E-Business Systems122 Questions
Exam 4: Documenting Information Systems129 Questions
Exam 5: Database Management Systems175 Questions
Exam 6: Relational Databases and SQL103 Questions
Exam 7: Controlling Information Systems: Introduction to Enterprise Risk Management and Internal Control161 Questions
Exam 8: Controlling Information Systems: Introduction to Pervasive Controls159 Questions
Exam 9: Controlling Information Systems: Business Process and Application Controls135 Questions
Exam 10: The Order Entrysales Oes Process134 Questions
Exam 11: The Billingaccounts Receivablecash Receipts Barcr Process134 Questions
Exam 12: The Purchasing Process141 Questions
Exam 13: The Accounts Payablecash Disbursements Apcd Process118 Questions
Exam 14: The Human Resources Process HR Management and Payroll Processes121 Questions
Exam 15: Integrated Production Processes IPP118 Questions
Exam 16: The General Ledger and Business Reporting GLBR Process107 Questions
Exam 17: Acquiring and Implementing Accounting Information Systems206 Questions
Select questions type
______________________________ is the assignment of an internal function to an outside vendor.
(Short Answer)
4.8/5
(37)
The two main inputs that trigger systems implementation are the ______________________________ and the ______________________________.
(Short Answer)
4.9/5
(42)
A user-directed test of the complete system in a test environment is called a(n) ____ test.
(Multiple Choice)
4.9/5
(43)
TB Figure 17.3 is taken from the text figure showing the systems selection task and documents.
Required:
Explode bubble 3.0 Systems Selection into a Level 1 DFD. The DFD should include the items listed below. The data flows for available hardware and physical requirements are listed twice because these data flows will each appear twice in the Level 1 DFD.
Process bubbles
3.1 Prepare requests for proposal
3.2 Evaluate vendor proposals
3.3 Assess software plan
3.4 Complete configuration plan
External entities
External sources
Hardware/ software vendors
Data flows
Approved configuration plan
Available hardware
Available hardware
Logical specification
Physical requirements
Physical requirements
Request for proposal
Software specifications
Suggested hardware resources
Vendor proposals

(Essay)
4.8/5
(38)
The purpose of the ______________________________ phase of the Information System Development process is to develop specifications for a new or revised system.
(Short Answer)
4.8/5
(27)
______________________________ costs are associate with but not directly attributable to the system or the system change.
(Short Answer)
4.8/5
(48)
With the modular approach to systems implementation, the new system either is implemented one subsystem at a time or is introduced into one organizational unit at a time.
(True/False)
4.9/5
(39)
______________________________ benefits are those that cannot be reasonably quantified, such as those that result from having improved information.
(Short Answer)
4.9/5
(39)
As depicted in the text, the approved configuration plan is the final output of the software and hardware study.
(True/False)
4.7/5
(36)
A(n) ______________________________ offers a traditional outsourcing mechanism whereby it hosts, manages, and provides access to application software and hardware over the Internet to multiple customers.
(Short Answer)
4.9/5
(41)
Which of the following ranks each alternative on its relative capability to satisfy the user's requirements (goals) for the system?
(Multiple Choice)
4.9/5
(38)
Which of the following is not a significant activity during the systems implementation phase?
(Multiple Choice)
4.8/5
(52)
The ______________________________ approach is also referred to as the phased approach.
(Short Answer)
4.9/5
(43)
The ______________________________ summarizes the implementation activities and provides documentation for operating the new system and for conducting the post-implementation review and systems maintenance.
(Short Answer)
4.8/5
(31)
The post-implementation review is an examination of a working system, conducted soon after the system's implementation.
(True/False)
4.8/5
(39)
______________________________ review the acquisition cycle and assess if and how internal controls have been impacted.
(Short Answer)
4.7/5
(36)
Structured systems design is a set of procedures performed to convert the logical specification into a design that can be implemented on the organization's computer system.
(True/False)
4.9/5
(44)
To validate vendor proposals for supplying computer hardware, an organization will assess both a system's specifications and performance.
(True/False)
4.8/5
(49)
Systems developed using structured systems design techniques are more costly over the life of the system because maintenance of such structured systems is problematic.
(True/False)
4.8/5
(37)
Showing 141 - 160 of 206
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)