Exam 14: Determining Project Progress and Results
Exam 1: Introduction to Project Management49 Questions
Exam 2: Project Selection and Prioritization52 Questions
Exam 3: Organizational Capability: Structure,Culture and Roles50 Questions
Exam 4: Chartering Projects39 Questions
Exam 5: Stakeholder Analysis and Communication Planning46 Questions
Exam 6: Defining Scope and Constructing Work Breakdown Structures WBS44 Questions
Exam 7: Scheduling Activities56 Questions
Exam 8: Resourcing Projects45 Questions
Exam 9: Budgeting Projects46 Questions
Exam 10: Project Risk Planning45 Questions
Exam 11: Project Quality Planning and Project Kick-Off45 Questions
Exam 12: Project Supply Chain Management45 Questions
Exam 13: Leading and Managing Project Teams46 Questions
Exam 14: Determining Project Progress and Results44 Questions
Exam 15: Finishing the Project30 Questions
Select questions type
All of the following accurately describe earned value management EXCEPT:
Free
(Multiple Choice)
4.9/5
(34)
Correct Answer:
C
In order to determine that a project is progressing adequately,a project manager could use a balanced scorecard approach to evaluate the organization along supplier,external business,risk and human resource perspectives.
Free
(True/False)
4.9/5
(52)
Correct Answer:
False
A tolerance limit is what the customer will accept,whereas a control limit reflects what the process can consistently deliver when things are behaving normally.
Free
(True/False)
4.7/5
(31)
Correct Answer:
True
Project managers interested in controlling quality on projects will often concentrate upon project inputs.Which of the following are important considerations for the project managers concentrating on inputs to ensure project quality?
(Multiple Choice)
4.8/5
(35)
Control quality generally includes all of the following EXCEPT:
(Multiple Choice)
4.9/5
(32)
One useful method of process improvement involves consideration of how another organization performs a process with an eye toward determining how to improve your own performance.This method is known as:
(Multiple Choice)
4.7/5
(45)
Your most recent project performance report indicates that your cumulative Schedule Performance Index (SPI)is .85 and your cumulative Cost Performance Index (CPI)is .90.What conclusions can you draw from these performance indices? What actions might you take to address project performance based on these results?
(Essay)
4.9/5
(38)
It is often costly,difficult or even impossible to inspect an entire sample.When that is the case,it is best to inspect the population.
(True/False)
4.8/5
(33)
Project managers should empower team members to the extent possible,yet control to the extent necessary.
(True/False)
4.8/5
(33)
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report
(October 31,20XX)
-Consider the project performance report presented in figure 14.1.What valid conclusion can you draw regarding the project schedule performance as of October 31,20XX?

(Multiple Choice)
4.8/5
(26)
In a control chart,a point that occurs above the upper control limit typically means that some sort of special cause is creating the variation and requires a specific intervention.
(True/False)
4.8/5
(39)
Describe the three different categories of risk events that occur during the control risk process,and some of the risk resolution strategies that might be used for each.
(Essay)
4.8/5
(36)
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report
(October 31,20XX)
-Consider the project performance report presented in figure 14.1.As a project manager,these results should lead you to...

(Multiple Choice)
4.7/5
(35)
The Cost Variance (CV)is a measure of cost efficiency of budgeted resources on a project,expressed as the ratio of earned value (EV)to actual cost (AC).
(True/False)
4.9/5
(27)
While the manage communications process is underway,effective information distribution often requires the project manager and team to accomplish all of the following activities EXCEPT:
(Multiple Choice)
4.7/5
(37)
When reporting performance to sponsors and management,it is often helpful to organize the information in terms of three time horizons: past,current and future.
(True/False)
4.8/5
(28)
In agile projects,communication is frequent and rapid.Progress report meetings are held every morning as brief 15 minute standup meetings.
(True/False)
4.8/5
(29)
The process of reviewing all change requests,approving changes,and managing changes to deliverables,organizational process assets,project documents and project management plan; and communicating their disposition,is known as:
(Multiple Choice)
4.8/5
(34)
Define integrated change control and briefly explain how it is accomplished in an organization.
(Essay)
4.9/5
(31)
Earned Value (EV)is the authorized budget assigned to the scheduled work.
(True/False)
4.8/5