  Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31,20XX) -Consider the project performance report presented in figure 14.1.Your analyst has determined that your estimate to complete (ETC)is $226,000.Based on your performance to date and assuming future performance will proceed at the same level of efficiency as past performance,what is your estimate at completion (EAC)? Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31,20XX) -Consider the project performance report presented in figure 14.1.Your analyst has determined that your estimate to complete (ETC)is $226,000.Based on your performance to date and assuming future performance will proceed at the same level of efficiency as past performance,what is your estimate at completion (EAC)?

(Multiple Choice)
4.8/5
(37)

The Schedule Performance Index (SPI)is a measure of schedule efficiency on a project,expressed as the ratio of earned value (EV)to planned value (PV).

(True/False)
4.9/5
(36)

Inspection is keeping errors out of process while prevention is trying to find errors so they do not get to the customer.

(True/False)
4.9/5
(37)

Change control includes which of the following activities?

(Multiple Choice)
4.8/5
(32)