Exam 12: Purchasing and Supply Chain Analysis: Tools and Techniques
Exam 1: Introduction to Purchasing and Supply Chain Management46 Questions
Exam 2: The Purchasing Process77 Questions
Exam 3: Purchasing Policy and Procedures28 Questions
Exam 4: Supply Management Integration for Competitive Advantage66 Questions
Exam 5: Purchasing and Supply Management Organization71 Questions
Exam 6: Supply Management and Commodity Strategy Development74 Questions
Exam 7: Supplier Evaluation and Selection68 Questions
Exam 8: Supplier Quality Management94 Questions
Exam 9: Supplier Management and Development: Creating a World-Class Supply Base84 Questions
Exam 10: Worldwide Sourcing76 Questions
Exam 11: Strategic Cost Management75 Questions
Exam 12: Purchasing and Supply Chain Analysis: Tools and Techniques51 Questions
Exam 13: Negotiation and Conflict Management97 Questions
Exam 14: Contract Management92 Questions
Exam 15: Purchasing Law and Ethics97 Questions
Exam 16: Lean Supply Chain Management72 Questions
Exam 17: Purchasing Services93 Questions
Exam 18: Supply Chain Information Systems and Electronic Sourcing57 Questions
Exam 19: Performance Measurement and Evaluation58 Questions
Exam 20: Purchasing and Supply Strategy Trends35 Questions
Select questions type
A ____ is one in which the set of steps or activities that make up the activity occur one after the other.
(Multiple Choice)
4.8/5
(33)
Which of the following is false regarding when to use the learning curve?
(Multiple Choice)
4.8/5
(38)
There is a strong correlation between effective planning and successful project outcomes.
(True/False)
4.7/5
(43)
In a PERT network,which of the following is not one of the times shown?
(Multiple Choice)
4.9/5
(39)
The work force factor of the learning curve refers to the ability of the worker on the job to learn and improve through repetitive effort and increased efficiency but not the effort by management to pursue productivity gains.
(True/False)
4.9/5
(31)
In a PERT network,the difference between the ____ and the ____ is slack.
(Multiple Choice)
4.8/5
(41)
When using quantity discount analysis,the key calculation is the incremental cost of each additional unit at different quantity levels.
(True/False)
4.9/5
(44)
Many organizations are attempting to develop new products concurrently rather than sequentially,which not only saves time and money but also allows agreement on major issues early in the process.
(True/False)
4.8/5
(33)
Value analysis is traditionally applied to tangible products and as such cannot be applied to services.
(True/False)
4.7/5
(40)
Each activity in PERT has three time estimates: (1)most likely,(2)pessimistic,and (3)optimistic.
(True/False)
4.8/5
(45)
Because most processes move across functional boundaries,it is illogical to have those groups involved with mapping and improving the process.
(True/False)
4.8/5
(42)