Exam 16: Pert CPM models for project management
Exam 1: Introduction24 Questions
Exam 2: Linear programming: Basic Concepts84 Questions
Exam 3: Linear programming: Formulation and applications57 Questions
Exam 4: Theart of modeling with spread sheets31 Questions
Exam 5: What-If Analysis for linear programming57 Questions
Exam 6: Network optimization problems48 Questions
Exam 7: Using binary integer programming to deal withy es-Or-No decisions28 Questions
Exam 8: Non linear programming52 Questions
Exam 9: Decision Analysis78 Questions
Exam 10: Forecasting76 Questions
Exam 11: Queuing models74 Questions
Exam 12: Computer simulation: Basic Concepts44 Questions
Exam 13: Computer simulation with risks olver platform47 Questions
Exam 14: Solution concepts for linear programming45 Questions
Exam 15: Transportation and assignment problems48 Questions
Exam 16: Pert CPM models for project management92 Questions
Exam 17: Goal programming21 Questions
Exam 18: Inventory management with known demand64 Questions
Exam 19: Inventory management with uncertain demand43 Questions
Exam 20: Computer simulation with crystal ball51 Questions
Select questions type
The latest starting time for an activity is equal to the latest finish time minus the duration of the activity
(True/False)
4.9/5
(40)
Activity C in a project network has an optimistic time estimate of five days,a most likely time estimate of seven days,and a pessimistic time estimate of nine days Its expected duration is approximately:
(Multiple Choice)
4.8/5
(26)
The standard deviation of the critical path is equal to the sum of the standard deviations of all the activities on the critical path
(True/False)
4.7/5
(35)
Crashing an activity will always reduce the duration of a project
(True/False)
4.7/5
(28)
Activities that are not on the critical path have a slack time equal to zero
(True/False)
4.9/5
(38)
When using linear programming to make crashing decisions,the objective is to minimize:
(Multiple Choice)
4.8/5
(30)
Only activities on the critical path are initial candidates for crashing
(True/False)
4.8/5
(32)
What is the probability that the critical path will be completed within 210 days?
(Multiple Choice)
4.7/5
(32)
The values assigned to the nodes in a project network are there to identify the precedence relationships
(True/False)
4.9/5
(37)
A project manager does not need to monitor each individual activity,just the overall project when looking at budget costs
(True/False)
4.8/5
(30)
Crashing cannot be accomplished by using different materials than originally planned
(True/False)
4.9/5
(34)
The activities with the longest durations in a project network are called critical activities
(True/False)
4.8/5
(43)