Which of the following are ways of crashing an activity?

(Multiple Choice)
4.8/5
(40)

The latest starting time for an activity is equal to the latest finish time minus the duration of the activity

(True/False)
4.9/5
(40)

Activity C in a project network has an optimistic time estimate of five days,a most likely time estimate of seven days,and a pessimistic time estimate of nine days Its expected duration is approximately:

(Multiple Choice)
4.8/5
(26)

The path with the greatest slack is:

(Multiple Choice)
4.9/5
(28)

-What is the estimated mean time for activity Y?

(Multiple Choice)
4.7/5
(29)

  -The expected duration of this project is: -The expected duration of this project is:

(Multiple Choice)
5.0/5
(40)

The standard deviation of the critical path is equal to the sum of the standard deviations of all the activities on the critical path

(True/False)
4.7/5
(35)

51 51

(Multiple Choice)
4.7/5
(36)

Crashing an activity will always reduce the duration of a project

(True/False)
4.7/5
(28)

Activities that are not on the critical path have a slack time equal to zero

(True/False)
4.9/5
(38)

Concerning PERT and CPM:

(Multiple Choice)
4.8/5
(36)

When using linear programming to make crashing decisions,the objective is to minimize:

(Multiple Choice)
4.8/5
(30)

52 52

(Multiple Choice)
4.9/5
(34)

Only activities on the critical path are initial candidates for crashing

(True/False)
4.8/5
(32)

What is the probability that the critical path will be completed within 210 days?

(Multiple Choice)
4.7/5
(32)

The values assigned to the nodes in a project network are there to identify the precedence relationships

(True/False)
4.9/5
(37)

A project manager does not need to monitor each individual activity,just the overall project when looking at budget costs

(True/False)
4.8/5
(30)

PERT/CPM can answer which of the following questions?

(Multiple Choice)
4.8/5
(36)

Crashing cannot be accomplished by using different materials than originally planned

(True/False)
4.9/5
(34)

The activities with the longest durations in a project network are called critical activities

(True/False)
4.8/5
(43)
Showing 21 - 40 of 92