Exam 16: Pert CPM models for project management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The latest finish of an activity is the earliest late start of any immediately preceding activity

(True/False)
4.8/5
(43)

The earliest start of an activity is the latest early finish of any immediately preceding activity

(True/False)
4.8/5
(33)

-What is the estimated mean time for project completion?

(Multiple Choice)
4.8/5
(34)

In PERT,the project duration will never exceed the expected duration of the critical path

(True/False)
4.8/5
(25)

-What is the estimated mean time for activity E?

(Multiple Choice)
4.9/5
(35)

The path with the greatest slack is:

(Multiple Choice)
5.0/5
(37)

The critical path is:

(Multiple Choice)
4.8/5
(34)

The length of the critical path is determined by adding the expected completion times for all the activities in the project

(True/False)
4.9/5
(39)

The mean critical path is the path through the project network that would be the critical path if the duration of each activity equals its mean

(True/False)
4.8/5
(19)

The earliest start time for an activity is:

(Multiple Choice)
4.8/5
(33)

-What is the estimated mean time for project completion?

(Multiple Choice)
4.8/5
(29)

A normal distribution is usually used to describe the form of the probability distribution of activity durations in the PERT three-estimate approach

(True/False)
4.8/5
(26)
Showing 81 - 92 of 92
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)