Exam 16: Pert CPM models for project management
Exam 1: Introduction24 Questions
Exam 2: Linear programming: Basic Concepts84 Questions
Exam 3: Linear programming: Formulation and applications57 Questions
Exam 4: Theart of modeling with spread sheets31 Questions
Exam 5: What-If Analysis for linear programming57 Questions
Exam 6: Network optimization problems48 Questions
Exam 7: Using binary integer programming to deal withy es-Or-No decisions28 Questions
Exam 8: Non linear programming52 Questions
Exam 9: Decision Analysis78 Questions
Exam 10: Forecasting76 Questions
Exam 11: Queuing models74 Questions
Exam 12: Computer simulation: Basic Concepts44 Questions
Exam 13: Computer simulation with risks olver platform47 Questions
Exam 14: Solution concepts for linear programming45 Questions
Exam 15: Transportation and assignment problems48 Questions
Exam 16: Pert CPM models for project management92 Questions
Exam 17: Goal programming21 Questions
Exam 18: Inventory management with known demand64 Questions
Exam 19: Inventory management with uncertain demand43 Questions
Exam 20: Computer simulation with crystal ball51 Questions
Select questions type
What is the estimated standard deviation in the time for activity E?
Free
(Multiple Choice)
4.9/5
(32)
Correct Answer:
C
In project network analysis,slack refers to the difference between:
Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
E
What is the estimated mean time for project completion?
Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
D
An activity has an optimistic time estimate of three days,a most likely time estimate of eight days,and a pessimistic time estimate of ten days The expected duration of this activity is:
(Multiple Choice)
4.8/5
(22)
When finding the approximate probability of project duration,it is necessary to know which of the following?
(Multiple Choice)
4.8/5
(29)
Given this information about activity H: ES = 10,EF = 15,LS = 16,and LF = 21,we can determine that the amount of slack associated with the activity is:
(Multiple Choice)
4.8/5
(33)
The project management strategy of injecting additional resources in order to reduce the length of the project is called:
(Multiple Choice)
4.8/5
(35)
-What is the probability that the critical path will be completed within 200 days?
(Multiple Choice)
4.8/5
(28)
The CPM method provides an excellent procedure for evaluating time-cost tradeoffs
(True/False)
4.7/5
(32)
There are four activities on the critical path Coincidentally,their standard deviations are all equal to 4 The standard deviation of the critical path is therefore equal to:
(Multiple Choice)
4.9/5
(32)
In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path
(True/False)
4.7/5
(39)
The slack of any activity is the amount of time that the activity can be delayed without delaying the completion of the project
(True/False)
4.8/5
(30)
-What is the estimated standard deviation in the time for activity E?
(Multiple Choice)
4.9/5
(28)
The earliest finish time for an activity is equal to the latest finish time minus the activity slack
(True/False)
4.9/5
(35)
In an Activity-On-Node project network,the nodes are used to separate an activity from each of its immediate predecessors
(True/False)
4.9/5
(29)
Project managers must often function in an environment that is beset with uncertainties
(True/False)
4.8/5
(37)
Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17 Its slack is:
(Multiple Choice)
4.8/5
(34)
In a project network the critical path is the sequence of activities which has:
(Multiple Choice)
4.7/5
(30)