Exam 16: Pert CPM models for project management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

What is the estimated standard deviation in the time for activity E?

Free
(Multiple Choice)
4.9/5
(32)
Correct Answer:
Verified

C

In project network analysis,slack refers to the difference between:

Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
Verified

E

What is the estimated mean time for project completion?

Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
Verified

D

An activity has an optimistic time estimate of three days,a most likely time estimate of eight days,and a pessimistic time estimate of ten days The expected duration of this activity is:

(Multiple Choice)
4.8/5
(22)

When finding the approximate probability of project duration,it is necessary to know which of the following?

(Multiple Choice)
4.8/5
(29)

Given this information about activity H: ES = 10,EF = 15,LS = 16,and LF = 21,we can determine that the amount of slack associated with the activity is:

(Multiple Choice)
4.8/5
(33)

The project management strategy of injecting additional resources in order to reduce the length of the project is called:

(Multiple Choice)
4.8/5
(35)

-What is the probability that the critical path will be completed within 200 days?

(Multiple Choice)
4.8/5
(28)

An important assumption in PERT calculations is:

(Multiple Choice)
4.8/5
(34)

The CPM method provides an excellent procedure for evaluating time-cost tradeoffs

(True/False)
4.7/5
(32)

There are four activities on the critical path Coincidentally,their standard deviations are all equal to 4 The standard deviation of the critical path is therefore equal to:

(Multiple Choice)
4.9/5
(32)

The standard deviation of a path is computed as:

(Multiple Choice)
4.9/5
(32)

In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path

(True/False)
4.7/5
(39)

The slack of any activity is the amount of time that the activity can be delayed without delaying the completion of the project

(True/False)
4.8/5
(30)

-What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.9/5
(28)

The earliest finish time for an activity is equal to the latest finish time minus the activity slack

(True/False)
4.9/5
(35)

In an Activity-On-Node project network,the nodes are used to separate an activity from each of its immediate predecessors

(True/False)
4.9/5
(29)

Project managers must often function in an environment that is beset with uncertainties

(True/False)
4.8/5
(37)

Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17 Its slack is:

(Multiple Choice)
4.8/5
(34)

In a project network the critical path is the sequence of activities which has:

(Multiple Choice)
4.7/5
(30)