Although PERT and CPM were originally developed for somewhat different types of projects,they are now nearly identical in terms of analysis and procedures

(True/False)
4.9/5
(45)

An activity in a project network cannot begin until all of the activities leading into that activity have been completed

(True/False)
4.8/5
(31)

The earliest finish time for an activity is equal to the latest finish time minus the duration of the activity

(True/False)
4.9/5
(28)

There is currently no method that permits activities and their immediate predecessors to overlap

(True/False)
4.7/5
(41)

The duration of the critical path is:

(Multiple Choice)
4.9/5
(36)

At which point does crashing of a project cease?

(Multiple Choice)
4.8/5
(33)

The critical path for the network shown is:

(Multiple Choice)
5.0/5
(36)

There are four activities on the critical path,and they have standard deviations of 1,2,4,and 2 days The standard deviation of the critical path is:

(Multiple Choice)
4.8/5
(37)

What is the probability that this project will be completed within 205 days?

(Multiple Choice)
4.9/5
(32)

In PERT,the path with the fewest activities is referred to as the critical path

(True/False)
4.9/5
(35)

In crashing a project,a manager will generally focus on activities which:

(Multiple Choice)
4.8/5
(26)

-What is the estimated slack time for activity D?

(Multiple Choice)
4.8/5
(36)

PERT/Cost:

(Multiple Choice)
4.8/5
(36)

-What is the estimated standard deviation in the time for activity Z?

(Multiple Choice)
4.7/5
(29)

Projects involve routine activities that are performed repeatedly

(True/False)
4.8/5
(24)

A Gantt chart of a project shows the scheduled start and finish times for activities

(True/False)
4.8/5
(34)

The sum of durations of the longest path in a project network indicates expected project completion time,and the activities are the critical activities

(True/False)
4.8/5
(25)

PERT/Cost is a systematic procedure to help a project manager bid on a project

(True/False)
4.8/5
(39)

The slack for path A-D-H-I is:

(Multiple Choice)
4.9/5
(46)

A manager has decided that an activity has a pessimistic estimate of 15 days,a most-likely estimate of 6 days,and an optimistic estimate of 3 days The expected duration of this activity is 6 days

(True/False)
4.9/5
(34)