Exam 16: Pert CPM models for project management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

An immediate predecessor of an activity must be completed before that activity can begin

(True/False)
4.8/5
(37)

If an activity is not on the critical path,then the project cannot be delayed if that activity is delayed

(True/False)
4.9/5
(33)

When calculating the probability that a project will finish by a certain time,the approximation that is obtained is usually lower than the true probability

(True/False)
4.7/5
(33)

The path in a project network with the average duration is the critical path

(True/False)
4.8/5
(40)

The PERT three-estimate approach can be used to determine the probability that a project will be completed by a certain time

(True/False)
4.9/5
(41)

Which of the following is not a feature of PERT/CPM?

(Multiple Choice)
4.8/5
(30)

The critical path for the network shown is:

(Multiple Choice)
4.9/5
(33)

PERT/Cost can be used to monitor budget overruns

(True/False)
4.8/5
(32)

AON project networks have which of the following advantages over AOA networks?

(Multiple Choice)
4.8/5
(37)

If the variance of an activity duration is equal to 1 then all the durations are the same

(True/False)
5.0/5
(26)

What is the estimated slack time for activity A?

(Multiple Choice)
5.0/5
(31)

A forward pass is the process of moving forward through the project network to determine the latest start times and latest finish times of each activity

(True/False)
4.9/5
(36)

The project network diagram describes sequential relationships among major activities in a project

(True/False)
4.8/5
(36)

The slack of an activity is the difference between the latest finish and the earliest finish times

(True/False)
4.8/5
(32)

If two paths are tied for the longest duration,both would be considered to be critical paths

(True/False)
4.9/5
(29)

  -The expected duration of this project is: -The expected duration of this project is:

(Multiple Choice)
4.7/5
(27)

What is the estimated mean time for activity E?

(Multiple Choice)
4.7/5
(39)

A common assumption when using PERT/Cost is that the costs are incurred at a constant rate throughout the duration of an activity

(True/False)
4.9/5
(45)

-What is the estimated slack time for activity W?

(Multiple Choice)
4.9/5
(34)

When making a backward pass through a project network,you must start at the finish node

(True/False)
4.7/5
(31)
Showing 61 - 80 of 92
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)