menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Quantitative Analysis for Management
  4. Exam
    Exam 11: Project Management
  5. Question
    Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates
Solved

Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates

Question 136

Question 136

Multiple Choice

Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively, compute the PERT variance for this activity.


A) 3
B) 6
C) 9
D) 18

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q131: Given the variability of the activity completion

Q132: Given an activity's optimistic, most likely, and

Q133: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1

Q134: Table 11-3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-3

Q135: In CPM, crashing an activity that is

Q137: Activity C of a project has a

Q138: Consider the project with the following estimates

Q139: A PERT/CPM network is a graphical display

Q140: Table 11-8<br>A mad scientist has identified the

Q141: Given the assumptions in PERT, the probability

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines