Multiple Choice
Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively, compute the PERT variance for this activity.
A) 3
B) 6
C) 9
D) 18
Correct Answer:

Verified
Correct Answer:
Verified
Q131: Given the variability of the activity completion
Q132: Given an activity's optimistic, most likely, and
Q133: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1
Q134: Table 11-3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-3
Q135: In CPM, crashing an activity that is
Q137: Activity C of a project has a
Q138: Consider the project with the following estimates
Q139: A PERT/CPM network is a graphical display
Q140: Table 11-8<br>A mad scientist has identified the
Q141: Given the assumptions in PERT, the probability