menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Quantitative Analysis for Management
  4. Exam
    Exam 11: Project Management
  5. Question
    Table 11-3 -According to Table 11-3, There Are Five Activities in a Five
Solved

Table 11-3 -According to Table 11-3, There Are Five Activities in a Five

Question 134

Question 134

Multiple Choice

Table 11-3
Table 11-3    -According to Table 11-3, there are five activities in a PERT project.What is the variance of the critical path? A) 5.222 B) 4.222 C) 1.222 D) 1.111
-According to Table 11-3, there are five activities in a PERT project.What is the variance of the critical path?


A) 5.222
B) 4.222
C) 1.222
D) 1.111

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q129: Given an activity's optimistic, most likely, and

Q130: Table 11-8<br>A mad scientist has identified the

Q131: Given the variability of the activity completion

Q132: Given an activity's optimistic, most likely, and

Q133: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1

Q135: In CPM, crashing an activity that is

Q136: Given an activity's optimistic, most likely, and

Q137: Activity C of a project has a

Q138: Consider the project with the following estimates

Q139: A PERT/CPM network is a graphical display

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines