menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Quantitative Analysis for Management
  4. Exam
    Exam 11: Project Management
  5. Question
    Activity C of a Project Has a Budgeted Cost of $40,000
Solved

Activity C of a Project Has a Budgeted Cost of $40,000

Question 137

Question 137

Short Answer

Activity C of a project has a budgeted cost of $40,000 and is 20% complete.The actual cost is $10,000.
(a)What is the value of work completed?
(b)What is the activity difference?

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q132: Given an activity's optimistic, most likely, and

Q133: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1

Q134: Table 11-3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-3

Q135: In CPM, crashing an activity that is

Q136: Given an activity's optimistic, most likely, and

Q138: Consider the project with the following estimates

Q139: A PERT/CPM network is a graphical display

Q140: Table 11-8<br>A mad scientist has identified the

Q141: Given the assumptions in PERT, the probability

Q142: The identification of the project activities and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines